Energy policy25 Nov 2026

Spain simplifies collective self-consumption and reserves 10% of tendered grid capacity for energy communities

Spain's government on 24 November approved two decrees that simplify collective self-consumption, recognise consumer-linked storage and regulate energy communities. For two years, 10% of the node capacity put out to tender will be released for renewable energy community projects.

EuroEnergy Newsroom · Spain · 2 min read

Panouri fotovoltaice în prim-plan pe acoperișul Facultății de Științe Economice a Universității din Cádiz; imagine ilustrativă
Foto: Emilio J. Rodríguez Posada · CC BY-SA 3.0 · Wikimedia Commons

Spain's Council of Ministers on Tuesday, 24 November, approved two royal decrees proposed by the Ministry for the Ecological Transition (MITECO): one changes the rules for electricity self-consumption and distributed storage, the other regulates renewable energy communities and citizen energy communities.

What was decided. The self-consumption decree updates Royal Decree 244/2019 and makes collective projects easier in apartment blocks, neighbourhoods, villages and industrial estates, including for participants without a roof of their own. A collective project can be registered with the first allocation agreement received by the distributor, and changes to the agreement only require the signatures of the consumers affected. The minimum commitment period drops to one month, a consumer can take part in several types of self-consumption at once, and a new modality lets consumers share only their surplus. Consumer-linked storage becomes a connection type compatible with any self-consumption modality.

Energy communities. The second decree sets the requirements for members and caps each member's vote at 40% of the total. For two years, 10% of the node capacity reserved for access tenders will be released for generation promoted by renewable energy communities, which also get their own quotas in the auction calendar. According to the ministry, IDAE's CE Implementa programme has so far supported 262 communities with €108.4 million from the Recovery Plan.

The figures. The Self-Consumption Alliance, quoted by El Periódico de la Energía, called the approval a “long-awaited advance” and noted that Spain had 9.2 GW of self-consumption installed at the end of 2025. At the same meeting, the government approved minimum requirements for installations connected to the grids which, according to Europa Press, extend access capacity for new consumers from 60% to 96% of nodes.

What comes next. MITECO will soon put a further update to public consultation: better protection for self-consumers against activation delays by distributors and extension of the 5,000-metre limit between generation and consumption to hydro plants and storage facilities.

Real-time data for the country is on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page