Akkuyu: hot and cold tests begin at unit 1, the last stage before nuclear fuel loading
The first unit of the Akkuyu nuclear power plant, built by Rosatom in Mersin province, has entered hot and cold testing after approval from the Turkish regulator. The primary circuit will be brought to 285 °C and 16.5 MPa, and Rosatom hopes nuclear fuel can be loaded as early as December.
EuroEnergy Newsroom · Türkiye · 2 min read
Unit 1 of the Akkuyu nuclear power plant, Turkey’s first, has entered the hot and cold testing stage, the last before the physical start-up of the reactor, Rosatom and Akkuyu Nuclear announced, according to Strana Rosatom, Enerji Günlüğü and World Nuclear News. Rosatom Director General Alexei Likhachev said the Turkish regulator had approved the tests and specialists had already started work.
What is being tested. All equipment in the primary and secondary circuits will run under operating conditions: checks cover the strength of equipment and piping, vibration, safety systems and the reactor control and protection systems. The reactor contains dummy fuel assemblies, not nuclear fuel, and the energy needed comes from an external source.
The figures. According to Akkuyu Nuclear, quoted by World Nuclear News, the primary coolant, desalinated water, will be gradually brought to 285 °C and 16.5 MPa, a pressure comparable to that at a depth of 1,650 metres. The plant will have four VVER-1200 reactors of 1,200 MW each, 4,800 MW in total, and is expected to generate about 35 billion kWh a year, roughly 10% of Turkey’s needs, according to Strana Rosatom.
What was said. “We are now not a step but literally half a step away from physical start-up,” Likhachev said. Akkuyu Nuclear CEO Sergei Butckikh said the unit’s readiness for start-up will be confirmed on the basis of the results of all tests scheduled for this stage.
What comes next. The tests will be followed by an inspection of the main and auxiliary equipment, after which the Turkish regulator will decide on a permit to load uranium fuel. Likhachev told the TASS agency he hoped fuel could be loaded as early as December and physical start-up begun this year, according to World Nuclear News.