Grid24 Nov 2026

Balearic Islands: ANACA accuses Red Eléctrica of drilling without a licence at Maristany for the second cable to the mainland

The ANACA association in Alcúdia says, based on town hall files, that Red Eléctrica carried out geotechnical surveys in the protected Maristany wetland without a municipal licence, for the route of the second Peninsula–Mallorca power link. The company says the work remains halted until it obtains the licence and that the project is under environmental assessment.

EuroEnergy Newsroom · Spain · 2 min read · updated 25 Nov 2026

Stația electrică de 220 kV Es Bessons, lângă Manacor, în Mallorca, cu stâlpi și linii de înaltă tensiune; imagine ilustrativă
Foto: INDALOMANIA · CC BY-SA 3.0 · Wikimedia Commons

The Association for a New Agreement on the Alcúdia Cable (ANACA) accuses Red Eléctrica (REE) of carrying out geotechnical surveys in the Maristany wetland, in northern Mallorca, without the required municipal permits and without the consent of the landowners. The work is meant to validate the route of the second electricity interconnection between the Iberian Peninsula and the Balearic Islands, Europa Press and Diario de Mallorca reported on 22 and 23 November.

What the files show. Alcúdia town hall gave the association access to the documents through a decree dated 19 November. A municipal technical report concludes that the surveys “did not have any enabling title” of an urban-planning or municipal nature. On 11 June REE had stated that all the work had the necessary permits; on 16 June an environmental officer of the Balearic government stopped it and filed an infringement report. On 18 June a town hall inspector found that one of the boreholes had been started in a coastal protection zone without authorisation.

Permit timeline. Authorisation to drill in a wetland was still being processed on 14 August, according to the Balearic government. The prior notice filed by REE on 27 August was declared ineffective by Decree 2026-3298 of 10 September, and on 14 September the company applied for a building licence for the same boreholes; the file is still pending. ANACA says it will oppose the legalisation of the surveys, will refer the matter to the Consell de Mallorca’s Territorial Protection Agency and to Spain’s Ministry for the Ecological Transition, and is preparing a court challenge.

The company’s position. REE says the surveys are needed to show that the wetland can be crossed by horizontal directional drilling, precisely to avoid harming it, that they will remain halted until the municipal licence is granted and that it carries out “no work without the corresponding permits”. According to Última Hora, the planned drilling is 580 metres long and up to 18 metres deep. Maristany is a Special Protection Area for Birds in the Natura 2000 network.

Background. The subsea cable is to make landfall at Sa Ferradura, between the bays of Alcúdia and Pollença, and the converter station is to be built in the Na Lloreta industrial estate, next to the Sant Martí 220/66 kV substation, following the onshore route agreed in July 2025 by the authorities, REE and residents. According to the company, the project is under environmental assessment at the Ministry for the Ecological Transition after the public consultation ended.

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page