Canary Islands: government approves by decree the 1.92 MW Camposanto I solar plant in Arico, Tenerife
The Canary Islands government has approved, in a decree published on 23 November in the Official Gazette, the construction of the Camposanto I photovoltaic plant in Arico, in southern Tenerife, with 3,705 panels. The 1.92 MW installation, promoted by Quintercon, is expected to produce about 3,521 MWh a year.
EuroEnergy Newsroom · Spain · 2 min read · updated 25 Nov 2026
The Canary Islands government has approved the construction of the 1.92 MW Camposanto I photovoltaic plant in the municipality of Arico, in the south of Tenerife. Decree 183/2026, adopted at the government meeting of 16 November, was published on Monday, 23 November, in the Official Gazette of the Canary Islands. The project is promoted by the company Quintercon S.L.
The figures. According to the decree, the plant has a peak capacity of 2 MWp, achieved with 3,705 modules of 540 Wp mounted on fixed structures driven into the ground, and 12 inverters. A 2,200 kVA transformer station raises the voltage from 630 V to 20 kV, and a 1,350-metre underground medium-voltage line carries the power to the connection point on the distribution grid. Estimated output is 3,520.93 MWh a year, with a reduction of 5,029.9 tonnes of CO2 annually, for an investment of about €393,652. The daily El Día equates the output with the annual consumption of around 1,000 homes.
The procedure. The project was declared of general interest in November 2024. Because no specific planning rules apply to the rural land, the government used the exceptional procedure in Article 6 bis of the Canary electricity sector law, which allows construction without an ordinary planning licence and requires plans to be adapted at their next substantial amendment. Arico town hall issued no opinion, and the Cabildo of Tenerife found no inconsistency with the island plan. The biodiversity service considered the installation viable provided the environmental monitoring plan is strictly applied, as the area is a priority zone for birds.
Background. The decree notes that transmission grid planning set a target of 164 MW of solar power for 2026 in the Tenerife–La Gomera electricity system, and installed capacity is below that target. The same mechanism was used in October for the 4.5 MW La Estrella plant in Arona, despite opposition from the town hall and the Cabildo, Diario de Avisos reported.
What comes next. According to El Día, the decree does not set a date for the start of works or for commissioning.