Spain awards €56 million to three 44.5 MW batteries next to renewable plants in Granada
Spain's Ministry for the Ecological Transition on 25 November awarded €56 million in ERDF funds to three storage systems hybridised with renewable generation in Huéneja, Dólar and Ferreira, in the province of Granada. According to the IDAE resolution, each has 44.5 MW and 183.94 MWh, and the money was freed up when two beneficiaries withdrew.
EuroEnergy Newsroom · Spain · 2 min read
Spain's Ministry for the Ecological Transition and the Demographic Challenge (MITECO) on Wednesday, 25 November, awarded €56 million to three energy storage projects in the province of Granada, in the municipalities of Huéneja, Dólar and Ferreira, in the Marquesado del Zenete area. All three are storage systems hybridised with renewable generation, funded through the PINALM programme, co-financed by EU ERDF funds 2021–2027, the Institute for the Diversification and Saving of Energy (IDAE) announced.
The figures. According to the award resolution published by IDAE, each of the three batteries – BAT Huéneja, BAT Dólar 3 and BAT Ferreira 2 – has a capacity of 44.5 MW and 183.94 MWh, with eligible costs of €40.49 million per project. The first two receive €20,417,340 each and the third €15,264,895, for a total of €56,099,575. Together the projects add up to 133.5 MW and about 552 MWh. The resolution lists the same applicant for all three.
Why now. The projects had been on the waiting list when the general call was resolved in December 2025. On 19 October 2026 the withdrawals of two original beneficiaries in Andalusia were accepted, freeing up the money, and the holders of the three files accepted the aid on 13 November, the IDAE document shows. The works must be completed by 31 December 2029.
Context. In total, the PINALM programme has allocated €826 million to 130 storage projects, mainly hybrids with renewables, followed by stand-alone batteries, thermal storage and pumped hydro. Once in operation, they will add 2.2 GW of power and 9.4 GWh of storage capacity, according to the ministry. The call received more than 1,700 applications, and the initial budget of €700 million was raised by 17%, MITECO said. Together with lines funded by NextGenEU, public support for storage exceeds €1,500 million.