An analysis by consultant Dejan Stojadinović shows Serbia paid renewable energy producers about EUR 1.52 billion from mid-2013 to the end of 2025 for 13.6 TWh. Importing the same amount would have cost about EUR 1.47 billion, so the difference is roughly EUR 50 million.

EuroEnergy Newsroom · Serbia · 2 min read

Turbine eoliene ale parcului de la Alibunar, în Banat, lângă un drum, cu o turbină mare în prim-plan; imagine ilustrativă
Foto: Ivan25 · CC BY-SA 4.0 · Wikimedia Commons

Serbia’s feed-in tariff system for renewable electricity cost about EUR 1.52 billion from mid-2013 to the end of 2025, according to an analysis by energy consultant Dejan Stojadinović, published by Balkan Green Energy News and carried on 22 November by the Biznis.rs portal. The contract data come from the list of contracts concluded by Elektroprivreda Srbije (EPS), dated 19 August 2026.

The figures. In return for these payments, Serbia received 13.6 TWh of electricity, equivalent to about 36% of the country’s annual output in 2025. The author estimates that importing the same amount would have cost about EUR 1.47 billion, leaving a difference of roughly EUR 50 million. Consumers covered 68% of the cost, about EUR 1.035 billion, through the renewable energy fee on their bills, and EPS the remaining 32%, about EUR 485 million, including around EUR 20 million in balancing costs.

The capacity. A total of 320 plants with 619 MW of capacity were built, almost 7% of Serbia’s generating capacity, with investments of about EUR 1.5 billion. Most of it comes from eight wind farms with 400 MW, followed by 138 small hydropower plants (90 MW), 53 biogas plants (54 MW), 12 high-efficiency cogeneration units (36 MW), the Vinča waste-to-energy plant (30 MW) and 107 solar plants (9 MW).

The contracts. Since mid-2014, 378 feed-in contracts have been signed, all for 12 years: 232 are active, 120 have expired, 26 were terminated, and another 19 expire by the end of 2026. The analysis also estimates about 8.1 million tonnes of avoided CO2.

The assessment. Stojadinović considers that the system fulfilled its purpose and was necessary to launch Serbia’s renewable energy sector. In his view, the difference of about EUR 50 million is outweighed by the domestic market, the experience and the skilled workforce built up over these years.

Real-time data for the country are on the country page.

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page