Electricity20 Nov 2026

First barges with Indonesian coal leave Constanța for Serbia; in August EPS received only 20% of planned deliveries

Elektroprivreda Srbije (EPS) confirmed to the Tanjug agency that the first barges carrying Indonesian coal have left the port of Constanța for Serbia after water levels on the Danube improved. River transport had been blocked for months: only 20% of planned quantities arrived in August, and less than half in September and October.

EuroEnergy Newsroom · Serbia · 2 min read

Termocentrala Nikola Tesla de lângă Obrenovac, cu coșuri roșu-albe, văzută peste linii de înaltă tensiune și conducte, lângă satul Urovci
Foto: Mickey Mystique · CC BY-SA 3.0 · Wikimedia Commons

Elektroprivreda Srbije (EPS) confirmed to the Tanjug agency on Thursday, 19 November, that the first barges loaded with coal from Indonesia have set off from the Romanian port of Constanța for Serbia. The departure was made possible by a more favourable hydrological situation on the Danube, after months in which river transport from Constanța was almost impossible.

The figures. According to EPS, only 20% of the planned coal quantities reached Serbia in August, and less than half in September and October. The company did not say how many barges have left, what tonnage they carry or when they are expected, the newspaper Srpske novine notes. The same outlet recalls that tender documents, reported earlier by the Beta agency, provide for 920,000 tonnes of Indonesian coal, transshipped in Constanța and carried by barge and rail to the TENT B power plant.

Why it matters. High-calorific Indonesian coal is used to improve the quality of the Kolubara lignite burned at the Obrenovac power plants, above all at TENT B. Without it, EPS explains, power output falls, operating costs rise because of additional fuel oil use, and the availability of some units is affected.

Measures taken. Low Danube levels also reduced output at the river’s hydropower plants. To keep electricity production stable, EPS urgently brought coal from Kostolac to TENT A. Over the summer the company expanded the capacity of the Kostolac coal yard by 10% and stepped up mining to secure more good-quality coal for the TENT A units.

The strategy. EPS says it is pursuing diversification of resources, energy sources, supply routes and transport modes to reduce its exposure to market and logistics risks. The company cites the transport of Kostolac coal to Obrenovac and the use of several ports as examples.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page