Netherlands: Brabant tests in five areas how almost 30,000 homes can be built on a full power grid
The province of North Brabant extended its crisis approach to electricity grid congestion on 19 November and is launching five grid-aware construction pilots in Breda, Tilburg, ’s-Hertogenbosch, Eindhoven and Helmond. Five further grid sections, where congestion is blocking housing and vital services, are being added to the crisis approach.
EuroEnergy Newsroom · Netherlands · 2 min read
The Dutch province of North Brabant announced on Thursday, 19 November, that it is extending its crisis approach to electricity grid congestion in order to make housing construction possible. Five grid-aware construction pilots are starting in the province’s four energy regions, in which the province, municipalities, developers and grid operators will look for ways to build new neighbourhoods where grid capacity is limited.
What was decided. The pilots are ’t Zoet in Breda (4,000–6,000 homes), Kenniskwartier in Tilburg (about 7,500), De Groote Wielen in ’s-Hertogenbosch (2,300–3,000), KnoopXL/Groots Gestel in Eindhoven (about 10,000) and Nieuw Brandevoort in Helmond (about 4,000). According to the trade publication Energeia, congestion is holding up plans for 28,000–30,000 homes in these areas. Neighbourhood batteries, smart energy management, collective energy systems, local generation and smart charging of electric vehicles are being examined.
The figures. The crisis approach already covered nine critical sections of the high-voltage grid. Five are now being added: one in Breda, one north of ’s-Hertogenbosch and three in the Eindhoven, Nuenen and Waalre area. There, grid safety is not at risk, but congestion is blocking housing and vital services such as hospitals, water companies and fire stations. “The question is not whether we want to build homes, but how we make that possible in a province with a full electricity grid,” said Bas Maes, the provincial executive member responsible for energy.
Background. The crisis approach was launched in September by the national government, the province, the energy regions, grid operators Enexis and TenneT and the regulator ACM, for an initial period of 12 months. For this winter, Enexis has announced extra measures at at least 26 locations in its area, and in the worst case part of the grid may be temporarily switched off. “We are expanding the electricity grid as quickly as possible and want to accelerate further,” said Rutger van der Leeuw, chief executive of Enexis Groep.
What comes next. The studies are to show which measures are promising and under what conditions homes can be built within existing grid capacity. The projects tie in with the action plan of the government task force on accelerating housing construction. At ’t Zoet, the first works should start at the end of 2028 or the beginning of 2029, and in Helmond the first homes are expected from 2028. “Brabant cannot afford to wait until all grid expansions are finished,” Maes added.
Real-time data for the country are on the country page