Grid21 Nov 2026

Netherlands: grid less full than thought in 40–60% of areas studied, SiRM analysis finds

Recalculated with more realistic forecasts of electricity demand, between 40% and 60% of the Dutch regional congestion areas studied would no longer exceed their capacity, according to a SiRM study commissioned by seven organisations. This could free up 900–1,100 MW on regional grids and 2.9–4.0 GW on the TenneT grid.

EuroEnergy Newsroom · Netherlands · 2 min read

Stâlpi și linii de înaltă tensiune deasupra unui câmp cultivat din zona Biesbosch, cu o centrală electrică în fundal; imagine ilustrativă
Foto: leopoldo de castro · CC BY 2.0 · Wikimedia Commons

A study by consultancy SiRM, published on 20 November, argues that a significant part of the congestion on the Dutch electricity grid stems from calculation assumptions. Grid operators often assume rapid growth in consumption, derived from the path to climate neutrality in 2050, while actual demand is growing more slowly: in about 80% of municipalities it has stayed flat or even fallen over the past ten years.

The figures. SiRM analysed 467 congestion studies published by the operators and kept 278 areas, from Enexis, Liander, Stedin and TenneT. Under the “delayed transition” scenario (VVT), about 40% of the regional areas no longer exceed their capacity; under the scenario based on the Klimaat- en Energieverkenning (KEV), about 60%. That would mean 900–1,100 MW of extra transport capacity on regional grids and 2.9–4.0 GW on TenneT’s high-voltage grid. The authors stress that the figures cannot be added together and that part of this capacity may already have been released in the meantime.

Flexibility. According to the study, regional operators spent only €1.6 million on congestion management in 2025, while making maximum use of controllable capacity could yield more than 2 GW extra in the areas analysed.

Context. In the first half of 2026, about 10 GW of demand was waiting for connection at the regional operators and about 34 GW at TenneT, according to SiRM. The study was commissioned by Energie-Nederland, VNO-NCW, VNCI, the data centre association DDA, Energie Samen, Energy Storage NL and Techniek Nederland. “If current forecasts show that there is room, that capacity must be made available as quickly as possible to the companies that are waiting,” said Femke Brenninkmeijer, chair of Energie-Nederland.

What next. The seven organisations are calling on the operators to update the congestion studies quickly and to adopt a single reporting standard. They stress that these measures do not replace grid expansion but can buy time until it is completed. The analysis covers only demand-side congestion; Energie-Nederland wants the forecasts for feed-in to be re-examined as well.

The country's real-time data are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page