Netherlands delays new wind farm rules, including the distance to homes, until 1 January 2028
The Netherlands has extended by one year, to 31 December 2027, the temporary regime that keeps the current environmental rules for existing wind farms in force, according to a decree published on Thursday in the Staatsblad. The new standards, which include a minimum distance between turbines and homes, are expected to take effect by 1 January 2028 at the latest.
EuroEnergy Newsroom · Netherlands · 2 min read
The Netherlands has once again postponed new environmental rules for onshore wind turbines. A royal decree of 11 November, published on Thursday, 19 November, in the Staatsblad, the Dutch official gazette, extends the temporary regime for existing wind farms, which was due to expire at the end of this year, until 31 December 2027. According to the explanatory memorandum, the new standards, including the minimum distance to homes, could take effect by 1 January 2028 at the latest, as the trade publication Energeia also reported.
What was decided. The decree, signed by King Willem-Alexander and by infrastructure state secretary Annet Bertram, changes a single deadline in the Besluit activiteiten leefomgeving: "31 December 2026" becomes "31 December 2027". A ministerial regulation published the same day in the Staatscourant makes the same change to the Omgevingsregeling. The regime applies to wind farms that had all final permits by 30 June 2021, and the government can set an earlier date if the new standards are ready.
Why. The temporary regime was introduced after a Council of State ruling on the Delfzijl Zuid wind farm found that the old turbine rules had not undergone the strategic environmental assessment required by EU law. The original deadline, 1 July 2025, has already been extended once. The explanatory memorandum calls the distance to buildings "a politically sensitive subject on which opinions differ".
What the government proposes. At the end of August, the cabinet chose a national distance of twice the tip height of the turbine, with the option of a smaller distance if it is justified, Solar Magazine reported. The draft sets a standard value of 45 dB Lden for noise and a limit of 47 dB Lden. Bertram acknowledged that the uncertainty has contributed to a decline in the number of onshore wind projects in preparation.
What comes next. The draft with the new standards is due to be sent to parliament at the end of 2026, after which the formal adoption procedure begins.
Real-time data for the country is on the country page
More news
Comments
Be the first to comment.