Denmark: Energinet's grid projects put at DKK 111 billion; nine in ten new projects on schedule

At the end of the third quarter Energinet had 180 transmission projects for electricity, gas and hydrogen, with total forecast costs of DKK 111.0 billion, up DKK 0.7 billion on the previous quarter. Of the projects approved since 2025, around nine in ten are expected to be completed on time, the operator says.

EuroEnergy Newsroom · Denmark · 2 min read · updated 25 Nov 2026

Doi stâlpi de înaltă tensiune lângă nodul de autostradă de la Odense, pe insula Fyn, care poartă liniile dintre Kauslunde și Middelfart
Foto: Hjart · CC BY-SA 4.0 · Wikimedia Commons

Danish transmission system operator Energinet published its project portfolio overview for the third quarter of 2026 on 23 November. It shows continued strong cost pressure, but also fewer schedule changes.

The figures. At the end of September Energinet had 180 ongoing transmission projects for electricity, gas and hydrogen. The total cost forecast reached DKK 111.0 billion, up DKK 0.7 billion in one quarter; the increase concerns electricity projects and stems mainly from a recalculation of reserves and price rises on projects approved before the change in the regulatory framework. During the quarter seven projects were postponed and two brought forward. In the first three quarters 18 projects were commissioned, and the company expects 31 for the whole of 2026, on a par with the record year 2025.

The new projects. Of the projects approved since 2025, around nine in ten are expected to be completed on time, and an even larger share to stay within budget, according to Energinet. "We see a portfolio that remains under pressure, but also a development in the right direction," said Nina Høegh Jensen, director of electricity transmission, adding: "But we are not there yet."

Context. The Bornholm Energy Island remains forecast at DKK 33.8 billion gross and is being carried out together with Germany, with EU funding, a state construction grant and a contribution from German operator 50Hertz. The forecasts for the gas network and the Danish Hydrogen Backbone pipeline are unchanged. In April 2026 the Danish National Audit Office (Rigsrevisionen) described the management of the grid expansion as "highly unsatisfactory", finding that around 70% of Energinet's projects were delayed.

What comes next. To reach the 31 commissionings expected for 2026, Energinet still has to complete 13 projects by the end of the year. The operator says new rules on environmental screening have already allowed some projects to be brought forward and should reduce the risk of delays.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page