Zealand: Energinet prepares 100 ha site for the island's largest high-voltage substation at Ringsbjerg
Energinet has begun preparing the site for the Ringsbjerg high-voltage substation near Køge, described as Zealand's largest, with completion due in 2029. The station will take power from the south of the island and send it towards the Copenhagen area through about 37 km of 400 kV underground cables, work on which started in November.
EuroEnergy Newsroom · Denmark · 1 min read
Danish transmission system operator Energinet has started work on the site of the future Ringsbjerg high-voltage substation in Køge Municipality, which the regional daily Dagbladet describes as the largest on Zealand. Soil is being moved, foundations are being prepared and the old Nordgården farm is being demolished, a job expected to be finished around New Year.
The figures. The site covers about 100 hectares along the Sydmotorvejen motorway; the substation itself, roughly 650 by 300 metres, takes up about a third, and the rest will become green space. Foundations and surrounding areas are expected to be ready in 2027 and the substation in 2029. "We have to be ready in 2029," project manager Claus Uhrenholt Lauritzen told Dagbladet.
The grid. Ringsbjerg will receive power from the south and send it towards the Copenhagen area. On 12 November Energinet announced the start of work on the 400 kV underground cables: about 29 km with two parallel systems to the new Lindehøj substation near Høje Taastrup and about 8 km to the existing Bjæverskov substation, with 74 directional drillings. According to the operator, the link adds about 1 GW of capacity, while Denmark's peak hourly demand is about 7 GW.
Context. The project is part of reinforcing the grid in the east of the island to handle growing volumes of green power and rising demand from transport and heating. A separate project, the new grid for South Zealand, Lolland and Falster, will add 3 GW when it enters service in 2033.
What comes next. Drilling continues into 2027, when cable laying begins, and archaeological excavations cover about 90,000 square metres. Energinet asks neighbours to expect machinery noise and more traffic while the work is under way.
Real-time data for the island are on the Sjælland · DK2 page
More news
Comments
Be the first to comment.
