Grid24 Nov 2026

ZSD completes the 110/22 kV Vajnory substation for northern Bratislava: investment of around €40 million

Distribution system operator Západoslovenská distribučná (ZSD) has completed the 110/22 kV Vajnory substation, which will supply the north of Bratislava. Around €40 million has been invested in the substation and associated lines, 35% of it EU co-financing, as part of the Danube InGrid smart grid project.

EuroEnergy Newsroom · Slovakia · 1 min read · updated 25 Nov 2026

Transformator de 110 kV într-o stație electrică de transformare, cu izolatoarele și barele de conexiune în prim-plan; imagine ilustrativă (stația Großgartach, Germania)
Foto: Zonk43 · CC BY-SA 4.0 · Wikimedia Commons

Západoslovenská distribučná (ZSD), the electricity distribution operator for western Slovakia, has completed construction of the Vajnory substation with 110/22 kV transformation, the company announced on Monday, according to the SITA news agency. Around €40 million has been invested in the substation and associated power lines, with 35% of the cost co-financed by the European Union.

What it brings. According to ZSD, the substation is to meet future electricity supply needs in the northern part of Bratislava and increase capacity to connect renewable sources and charging infrastructure for electric vehicles. “It will allow not only new consumption points to be connected, but will also improve the quality and reliability of distribution for existing customers currently supplied from surrounding substations such as Žabí Majer, Pezinok, Ostredky and Podunajské Biskupice,” said ZSD chairman Radoslav Haluška. The substation is designed to operate without permanent staff and will be remotely controlled from the company’s dispatch centre.

The figures. When construction began in March 2025, the cost was estimated at more than €30 million and completion was announced for the end of 2026, according to the Ministry of Economy and the TASR news agency. The substation is part of Danube InGrid, a €291 million European project of common interest involving ZSD, transmission operator SEPS and Hungarian distributor E.ON Észak-dunántúli Áramhálózati. ZSD’s planned investment in the project is €119 million, and grants from the Connecting Europe Facility amount to around €101.9 million, according to SITA.

What comes next. The ZSD substation will later be connected to the neighbouring 400/110 kV substation that SEPS is building in Vajnory. According to the Ministry of Economy, together they will form one of the key hubs of the Slovak power system.

Real-time data for the country is on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page