Austria: APG presents the final route of the 380 kV line through Carinthia, 193 km and around 700 pylons
Austrian transmission operator APG and Kärnten Netz present on Monday the definitive route of the 380 kV line between Lienz and Obersielach, which is 193 kilometres long and will have around 700 pylons. According to ORF Kärnten, the final route deviates by 25% from the preliminary one, while opponents dispute the need for the project.
EuroEnergy Newsroom · Austria · 2 min read
Austrian Power Grid (APG), Austria's transmission system operator, and regional distributor Kärnten Netz are presenting on Monday, 23 November, the so-called “Feintrasse” – the detailed route with the pylon locations – for the 380 kV line that is to cross Carinthia. According to ORF Kärnten, the 193-kilometre line links Obersielach, near Völkermarkt, with Lienz in East Tyrol and closes Austria's 380 kV ring.
The figures. ORF Kärnten writes that around 700 pylons are planned along a corridor 70 metres wide, and that their locations have already been fixed. The final route deviates by 25% from the preliminary route presented more than a year ago, following talks with the state, municipalities, landowners and residents. On the project page, APG says the new pylons will also carry Kärnten Netz's 110 kV line over around 173 kilometres, while around 140 kilometres of old 110 kV line will be dismantled.
What was decided. The Carinthian state government has called an extraordinary session on the “Netzraum Kärnten” project for Monday from 9 a.m., according to a statement from the state. After the government and the social partners, the project is to be presented to mayors in Villach, and eight information sessions are scheduled until 3 December in the affected areas of Carinthia and East Tyrol.
Context. Energy companies argue that the line is needed for the long-term supply of households and industry; industry expects Carinthia's electricity demand to double by 2040. Several citizens' initiatives and the FPÖ dispute this estimate, ORF notes. APG describes the project as closing the only gap in Austria's 380 kV ring and says the existing 220 kV lines are at the limit of their capacity. The European Union added the project to the list of Projects of Common Interest (PCI) with effect from 29 April 2026.
What comes next. The start of construction has not been set: the project needs several permits, including an environmental impact assessment, and objections are expected. According to ORF Kärnten, APG plans commissioning in 2035; the project page still gives a construction start in 2029 and commissioning in 2033.
The country's real-time data are on the country page
More news
Comments
Be the first to comment.
