Nuclearelectrica signs €400 million EIB loan for the refurbishment of Cernavodă Unit 1
Nuclearelectrica and the European Investment Bank signed on 16 November the first contract, worth €400 million, of the €800 million financing approved for the refurbishment of Unit 1 at Cernavodă. The project, estimated at around €3.1 billion, would extend the unit's operating life by 30 years.
EuroEnergy Newsroom · Romania · 1 min read
Nuclearelectrica and the European Investment Bank (EIB) signed on Monday, 16 November, a €400 million financing contract for the refurbishment of Unit 1 of the Cernavodă nuclear power plant. It is the first of the two contracts under the €800 million loan approved by the EIB Board of Directors on 15 July 2026.
The figures. According to the company, the EIB loan covers 25% of the total project value, estimated at about €3.1 billion excluding financing costs. The €800 million is split into two contracts of €400 million each, and the second is to be signed in 2027, depending on the project's stages. The loan has a maturity of up to 22 years, according to Agerpres and Digi24. Nuclearelectrica's financial director, Daniel Adam, described the contract as “the largest European Investment Bank financing for a company in Romania”.
What the project brings. The refurbishment should extend Unit 1's operating life by another 30 years, with the unit delivering 5 million MWh a year to the national power system, according to Nuclearelectrica. The first stage, identifying the works, was completed in 2022. The current stage covers detailed planning, contracting, procurement of long-lead equipment, infrastructure and permitting.
Context. Nuclearelectrica's shareholders approved taking the EIB financing at the extraordinary general meeting of 29 October 2026. EIB Vice-President Ioannis Tsakiris called the refurbishment an emblematic investment that helps ensure a stable electricity supply at affordable prices and with low carbon emissions. For the remaining costs, the company is negotiating with export credit agencies, commercial banks and other international financial institutions, according to Digi24.
What comes next. In the third phase, scheduled for 2027–2030, Unit 1 will be shut down for the actual refurbishment works.