Litgrid launches procurement of expert review for Harmony Link, the over €900 million interconnection with Poland
Lithuanian transmission system operator Litgrid has launched the procurement for the verification of design proposals and the expert review of the technical design of Harmony Link, the 220 kV overland line to Poland. Works in Lithuania are expected to start in the second quarter of 2027, with the link to be commissioned by the end of 2030.
EuroEnergy Newsroom · Lithuania · 2 min read
Lithuania’s electricity transmission system operator, Litgrid, announced on Friday, 20 November, the procurement of services for the verification of design proposals and the general expert review of the technical design for Harmony Link, the overland interconnection between Lithuania and Poland. The procurement has two lots and was preceded by a market consultation, according to the operator; the announcement was carried by LRT via the BNS agency.
What was decided. “Following the decision on the Harmony Link connection point in Lithuania, we are consistently moving on to the implementation stage. The expert review of the technical design is an important part of the process, which will help ensure high-quality design solutions and prepare for the future construction works,” said Vaidotas Stankevičius, head of Litgrid’s resilience programme implementation centre. In parallel, the tender for the design and construction of the Gižai transformer substation in Vilkaviškis district, the first of the project’s four works tenders, is continuing.
The figures. Harmony Link consists of new 220 kV double-circuit alternating current lines from the Ełk Bis substation, via the Norki and Wigry substations in Poland, to the future Gižai substation, plus the upgrade of the 220 kV Ostrołęka–Ełk Bis line. The total value exceeds €900 million: the maximum budget in Lithuania is €220 million, of which €147.2 million is EU funding, while investments in Poland are estimated at around €703 million, according to BNS. Once commissioned, commercial exchanges could reach 1,200 MW in both directions. The Gižai substation, covering about 35 hectares, will be the largest in Lithuania.
Background. The original option, a subsea direct current cable, was abandoned in April 2023, when Litgrid and the Polish operator PSE cancelled the tender due to rising costs of cables and converter stations. A subsequent study showed that the overland alternating current solution ensures comparable stability of the interconnected systems, according to PSE. The project has the status of special national importance and is co-financed by the Connecting Europe Facility.
What comes next. The route in Lithuania runs through Vilkaviškis district and the municipalities of Kalvarija and Marijampolė. Construction on Lithuanian territory is expected to start in the second quarter of 2027, with the interconnection to be energised by the end of 2030.
The country’s real-time data are on the country page
More news
Comments
Be the first to comment.
