Kazakhstan: two 1 GW wind farms with TotalEnergies and Masdar target commissioning in 2029
State-owned Samruk-Energy reviewed two 1 GW wind projects in Kazakhstan with TotalEnergies and Masdar, both with battery storage. Earthworks and foundation preparation are under way at the TotalEnergies project, first electricity is expected in the fourth quarter of 2028, and both wind farms are due to be commissioned in 2029.
EuroEnergy Newsroom · Kazakhstan · 2 min read
Samruk-Energy Chairman of the Management Board Ansar Aidarov met Nolwenn Delaunay, TotalEnergies Senior Vice President for Asia, the Middle East, Africa and Latin America, and Abdulla Zayed, Masdar Executive Director for Business Development and Project Development, the Kazakh company announced on 19 November. The talks covered joint wind projects with a total capacity of 2 GW.
Progress on site. The project with TotalEnergies is a 1 GW wind farm with a 300 MW/600 MWh storage system. "Earthworks and preparation of the wind turbine foundations are currently under way at the site," Samruk-Energy said. First electricity is expected in the fourth quarter of 2028 and full commissioning in 2029. The second project, with Masdar, also 1 GW and with energy storage, has been under construction since June 2026 and is also due to enter operation in 2029.
What was discussed. The parties talked about the joint venture between TotalEnergies Renewables S.A.S. and Masdar that will bring together their renewable portfolios in Asia; a joint holding with equal stakes will own the project companies in Kazakhstan. According to Samruk-Energy, the parties reaffirmed their earlier commitments and their intention to continue the projects.
The figures. According to TotalEnergies, cited in April by Energy Global, its wind farm, named Mirny, will have 150 turbines, costs $1.2 billion, about 75% of it externally financed, and has a 25-year power purchase agreement with the Kazakh state; the shareholders are TotalEnergies (60%), Samruk-Energy (20%) and KazMunayGas (20%). For the Masdar project in the Zhambyl region, the Energy Ministry announced at the groundbreaking on 29 June an investment of about $1.4 billion, 300 MW/600 MWh of storage and full commercial operation in the third quarter of 2029.
Context. According to the ministry, the Masdar wind farm is meant to help cover the energy deficit in the southern regions and cut CO₂ emissions by 2.5 million tonnes a year. Separately, the Trend agency reported on 19 November that the Asian Infrastructure Investment Bank is considering a 1 GW wind project in the Zhambyl region.