Kazakhstan: the 1,113.4 MW Turkestan gas-fired power plant is 62% built; the first 382 MW due in May 2027
The 1,113.4 MW “Turkestan” combined-cycle gas power plant in southern Kazakhstan has reached 62% of its construction and installation work, the government said after a visit by First Deputy Prime Minister Nurlybek Nalibaev. The first 382 MW are due to be fed into the grid in May 2027, and the government wants full commissioning by the end of 2027 to be studied.
EuroEnergy Newsroom · Kazakhstan · 2 min read
The “Turkestan” combined-cycle gas power plant, with a capacity of 1,113.4 MW, under construction in the Sairam district of Turkestan region, has reached 62% completion of its construction and installation work, the press service of Kazakhstan's government announced on 20 November after a site visit by First Deputy Prime Minister Nurlybek Nalibaev. At the start of the year, completion stood at about 15%.
The figures. There are 2,455 people working on the site, 2,281 on the day shift and 174 on the night shift. The main equipment has been delivered, and all four Siemens gas turbines are installed. The electrical networks are 96% complete, the supply gas pipeline is finished, and the 3.1 km access road has been put into service. Of the seven planned water wells, two already supply about 960 m³ a day, against the 240 m³ needed for the first stage.
The timetable. According to the government, the control start-up of the first unit is scheduled for the end of 2026. The first 382 MW are due to enter the grid in May 2027 and another 382 MW in August, bringing installed capacity to 764 MW in September 2027. Nalibaev asked for reaching full capacity by the end of 2027 to be examined. “Construction must not drag on; the work must be completed within the set deadlines,” he said.
Context. The plant is to supply Turkestan region, the city of Shymkent and Zhambyl region. According to the government, average consumption in Turkestan region is about 445 MW, while local generation is 136.5 MW. In March, the government presented the project as a 1,000 MW plant to be commissioned by the end of 2026; the investor is TOO “PGU Turkestan”, a subsidiary of the Samruk-Kazyna fund. The publication Kursiv recalls that in October the Ministry of Energy announced only 1.27 GW of new capacity in 2026, against 2.66 GW planned, with the delays linked to the modernisation of the CHP-3 plant in Almaty and the construction of the gas-fired plant in Turkestan.
What comes next. The government aims for Kazakhstan to have a stable electricity surplus by 2029.
More news
Comments
Be the first to comment.
