Italy joins MARI, the European mFRR balancing platform: GME announces go-live on 25 November

Italy's energy market operator GME announced on 25 November the operational start of the European platform for exchanging balancing energy from manually activated reserves (mFRR), developed under the MARI project. Terna had announced in September that it would take part from that date, after tests with market participants between 28 September and 13 November.

EuroEnergy Newsroom · Italy · 2 min read

Stâlp al unei linii de înaltă tensiune la Mardimago, în Veneto; imagine ilustrativă
Foto: Threecharlie · CC BY-SA 3.0 · Wikimedia Commons

Gestore dei Mercati Energetici (GME), Italy's energy market operator, announced on 25 November the operational start of the platform for exchanging balancing energy from manually activated frequency restoration reserves (mFRR), provided for in Article 20 of Regulation (EU) 2017/2195. The platform was developed under the European MARI project (Manually Activated Reserves Initiative). With the announcement, the updated technical provision DTF no. 03 rev.15 MPE also entered into force, setting the timing of sessions on the MGP, MI and MSD markets and on the nomination platform.

The preparation. Terna, the transmission system operator, had announced on 23 September that it would join the platform from 25 November 2026. GME and Terna then held test sessions with market participants on the IPEX platform between 28 September and 13 November to try out the new functions. On 3 November the regulator ARERA verified the compliance of the new agreement between Terna and GME that enables the connection to MARI (decision 405/2026/R/eel).

How it works. According to an analysis by Modo Energy, MARI is a shared European merit order: each transmission operator submits its balancing needs and the eligible bids of balancing service providers, and the platform runs an auction for every quarter-hour, selecting the cheapest bids that cover all needs. Accepted bids are paid the clearing price, whereas on the national balancing market (MB) each bid is paid its own price. Exchanges use the cross-border capacity left after the day-ahead and intraday markets.

What stays with Terna. At the start, Italy takes part only in MARI's scheduled auctions, and Terna keeps the MB market for local grid constraints and for activations outside the platform, Modo Energy writes. Balancing service providers continue to submit bids on the GME platform, as before.

Context. The platform went live in October 2022 with the four German transmission operators and ČEPS of Czechia. According to ENTSO-E, the most recent connections before Italy were France's RTE on 16 April 2026, Slovenia's ELES on 16 July and Hungary's MAVIR on 6 October.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page