Ireland: High Court reserves judgment on rules letting data centres run on fossil fuels for six years
Three environmental groups are asking Ireland’s High Court to quash the large energy users connection policy adopted by the regulator CRU, which allows new data centres to meet their demand from fossil fuels in the first six years. The regulator replied on 18 November that its primary role is security of supply, and the judge reserved judgment.
EuroEnergy Newsroom · Ireland · 2 min read
The High Court in Dublin heard on 17 and 18 November the challenge brought by Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth against the Commission for Regulation of Utilities (CRU). The groups are seeking to quash the large energy users connection policy, published by the regulator in December 2025, which ended the de facto moratorium in place since 2021 on connecting new data centres to the grid.
What the rules say. According to The Irish Times, a data centre can connect if it supplies as much electricity to the grid as it takes, by building or contracting generation on site or nearby. In the first six years that generation can use fossil fuels; after that, 80% must come from renewable sources such as wind or solar, while 20% can still come from gas or oil.
The arguments. The applicants, represented by barrister James Devlin, argue that the CRU breached the Climate Action Act of 2015 because it did not consider whether the policy would cause carbon budgets and emission ceilings to be exceeded. The regulator, represented by Eoin McCullough, replied that its primary role is to protect security of supply in the face of rising demand from data centres and that it lacks the power to impose express emissions-reduction requirements on operators.
The figures. According to Bloomberg, Ireland hosts about 89 data centres, which used 23% of metered electricity in 2025, up from 5% a decade earlier; gas generated 47% of the country’s electricity last year. Friends of the Earth Ireland says the data centres’ share could reach a third by the end of the decade.
What comes next. Judge Micheál O'Connell reserved judgment without announcing a date for the ruling. The environmental groups are seeking, among other reliefs, an order quashing the CRU’s decision to adopt the policy.
Real-time data for the country are on the country page.
More news
Comments
Be the first to comment.
