State-owned Elektroprivreda Srbije (EPS) is holding a public consultation in Nova Varoš on December 2 on the resettlement plan and the environmental and social study for the Bistrica pumped-storage hydropower plant. Meanwhile, the location conditions have been amended and the existing Radoinja dam is to be rebuilt.

EuroEnergy Newsroom · Serbia · 2 min read

Râul Uvac la Kokin Brod, lângă Nova Varoš, în coada lacului de acumulare Radoinja, cu un pod rutier în dreapta și dealuri împădurite
Foto: Bjoertvedt · CC BY-SA 4.0 · Wikimedia Commons

Elektroprivreda Srbije (EPS) announced on November 18 that it is organising a public hearing on the Resettlement Action Plan and on the study of the environmental and social aspects of the Bistrica pumped-storage hydropower plant (RHE) project. The meeting will take place on Wednesday, December 2, 2026, at 11:00 in the administrative building of the Limske hidroelektrane branch in Nova Varoš, in south-western Serbia.

What was announced. According to EPS, the consultation follows the guidelines of the Japan International Cooperation Agency (JICA) on environmental and social considerations, and residents and other stakeholders will receive information on the works and protection measures and will be able to take an active part. Balkan Green Energy News recalls that JICA is expected to approve a loan for construction and that the Japanese government approved the agency's participation in mid-2024, when the total value of the project was estimated at EUR 1.2 billion.

The figures. According to the Biznis.rs portal, the plant is to have about 660 MW and annual output of around 1,600 GWh; the Energetika.ba portal cites about 650 MW. The upper reservoir, Klak, will be formed by a dam on the Uvac river downstream of the Radoinja dam and will hold 108 million m³, while the lower reservoir will be the existing Potpeć lake on the Lim. The project is meant to help integrate about 1,500 MW of new renewable capacity.

Background. Energetika.ba, citing Ekapija, reports that Serbia's construction ministry has issued amended location conditions at the request of EPS. The main change concerns the Radoinja dam, which will be rebuilt to withstand an earthquake with a 3,000-year return period, so that the Radoinja and Klak reservoirs are fully separated. The designer is Energoprojekt Hidroinženjering.

What comes next. According to Biznis.rs, the building permit for the main plant and the tender for the works are expected in 2027, when the loan agreement with JICA is also due to be signed. In April, EPS submitted the request to set the scope of the environmental impact assessment study.

The country's real-time data are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page