Faroe Islands: SEV repairs 60 kV subsea cable and Veðranes line after two power cuts in Eysturoy

Faroese utility SEV finished repairs on Tuesday morning after two power cuts, on Sunday evening and Monday morning, in Norðoyggjar, Eysturoy and the Sundalagið area. The cause was a faulty joint on the subsea cable between Streymoy and Eysturoy, followed by the failure of an overloaded overhead line.

EuroEnergy Newsroom · Denmark · 2 min read

Stâlpi metalici cu zăbrele ai unei linii de 70 kV, în prim-plan, pe un deal din Tórshavn, cu case și marea în fundal; imagine ilustrativă
Foto: eneerhut · CC BY-SA 4.0 · Wikimedia Commons

The electricity company SEV, which runs the grid in the Faroe Islands, said on 25 November that both faults that cut power to the north of the archipelago early this week have been repaired and that the affected connections are back in operation.

What happened. On Sunday, 22 November, a cable fault cut supply in northern Eysturoy and in Norðoyggjar between 18:37 and 19:43, according to SEV. It later emerged that the fault was on the subsea cable between Streymoy and Eysturoy, on the Sund–Runavík link. Power was rerouted through overhead lines, and on Monday morning a line broke at Veðranes, above the village of Selatrað, “most likely because of too high a load”, the company wrote.

Monday’s outage. Norðoyggjar, parts of Eysturoy and the Sundalagið area lost power again. SEV’s head of operations, Eirikur Norðberg, told the radio at 9 a.m. that reconnection would probably take an hour; the company later expected 11 a.m., and at 11:03 all customers should have had power again, according to portal.fo. Vikublaðið also reported the outage, citing SEV’s website.

The repairs. The Veðranes line was restored on Monday; the equipment had to be carried up the hillside because the helicopter was not available. Meanwhile, crews located the cable fault: a joint between the subsea cable and the cable linking Rókin to the switching station in Runavík. The cable was dug free and work began late on Monday evening. Jointing a 60 kV subsea cable is “somewhat more challenging and time-consuming than usual”, SEV explained; by Tuesday morning both links had been repaired.

Context. The Faroese power system is isolated, with no connection to neighbouring countries’ grids, so the balance between generation and consumption is secured only by local power plants and the local grid, according to a Faroese government answer in the Løgting on 25 November.

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page