Croatia: wpd plans to replace the 11 turbines of the Orlice wind farm with three 6 MW units and a 10 MW battery
German company wpd is preparing to modernise the Orlice wind farm near Šibenik, in operation since 2009: its 11 Enercon turbines, totalling 9.6 MW, would be replaced by three 6 MW turbines, raising capacity to up to 20 MW. The project also includes a 10 MW battery energy storage system, according to Balkan Green Energy News.
EuroEnergy Newsroom · Croatia · 2 min read
German company wpd is preparing to modernise the Orlice wind farm near Šibenik, Balkan Green Energy News reported on 16 November. The project company Vjetroelektrana Orlice has submitted an environmental study to the Ministry of Environmental Protection and Green Transition, asking it to determine whether the project requires a full environmental impact assessment.
What changes. According to the documentation cited by the publication, the 11 existing turbines will be dismantled and replaced by three new turbines of 6 MW each, built on three new foundations at the sites of the old ones. Installed capacity would reach up to 20 MW, compared with 9.6 MW today. The project includes a battery energy storage system with a power of 10 MW. The investor also plans to restore about 1,500 metres of roads that will no longer be used with native vegetation.
The farm today. Orlice lies within the City of Šibenik, in Šibenik-Knin County, and was connected to the grid in December 2009. At its opening, wpd announced 11 Enercon turbines with a total of 9.6 MW and estimated output of 21 million kWh a year. According to the company, it was only the third wind farm connected to the grid in Croatia.
Context. Orlice is the second Croatian wpd wind farm proposed for modernisation. At the end of October, Balkan Green Energy News reported that at the 11.2 MW Trtar-Krtolin wind farm, the 14 turbines of 800 kW each would be replaced by no more than five new turbines, together with a battery of up to 10 MW and 20 MWh. For the 34.2 MW Katuni wind farm, wpd announced in 2023 a solar power plant on the same site. The company's largest wind farm in Croatia is Ponikve, on the Pelješac peninsula, with 38.6 MW.
What comes next. The ministry must decide whether the modernisation of Orlice requires a full impact study. The timetable of the works and the value of the investment do not appear in the published materials.
Real-time data for the country are on the country page
More news
Comments
Be the first to comment.