Switzerland: Infomaniak and Gruyère Energie plan a 2.5 MW data centre in Bulle that would supply 28 GWh of heat a year
Cloud provider Infomaniak and energy company Gruyère Energie have filed a building application for a data centre in Bulle whose heat would go entirely into the town's district heating. According to the companies, the site would supply around 28 GWh of heat a year and enter service in 2028.
EuroEnergy Newsroom · Switzerland · 2 min read
Swiss cloud provider Infomaniak and energy company Gruyère Energie have announced a data centre project in Bulle, in the canton of Fribourg, whose building application has been on public display since 13 November. The servers' heat is to be used entirely in Gruyère Energie's district heating network, according to the companies' press release, which was also distributed on 16 November.
The figures. The planned IT capacity is 2.5 MW, twice that of Infomaniak's D4 centre in Geneva. The building, designed for 170 racks, would occupy around 1,200 m². At full load, the 2.5 MW of electricity is expected to yield around 2.5 MW of heat continuously. According to Gruyère Energie's estimates, the site would supply around 28 GWh of heat a year to the network after the heat pumps, avoiding around 2.8 million litres of heating oil and up to 7,500 tonnes of CO₂.
How it works. Storage servers will be air-cooled, while computing and artificial intelligence servers will be cooled by liquid in a closed loop directly at the chips, allowing heat to be recovered at a higher temperature. Gruyère Energie's heat pumps then raise the temperature to network level. Cooling uses no cooling tower, evaporation or water withdrawal. Subject to contracts not yet signed, Infomaniak would build and operate the centre, while Gruyère Energie would provide the land, the heat recovery installations and 100% renewable electricity.
Context. Gruyère Energie's district heating network runs on more than 95% renewable energy, and its heat production is set to rise to 180 GWh by 2030. According to the companies, server heat complements, rather than replaces, local wood energy and a deep geothermal project of a Gruyère Energie subsidiary. Infomaniak, whose billed services grew by 26.5% in the first half of 2026, intends to finance the project from its own resources.
What comes next. Subject to permits, construction would begin in the first half of 2027, with commissioning planned for 2028.