Grid16 Nov 2026

Crete: €1.94 billion interconnection with Cyprus due by end-2031; marine surveys 60% complete

Greek transmission system operator ADMIE puts completion of the 1,000 MW, €1.94 billion Crete–Cyprus electricity interconnection, which starts from the Damasta station near Heraklion, at the end of 2031. Seabed surveys, at depths of up to 3,000 m, are 60% complete.

EuroEnergy Newsroom · Greece · 2 min read

Satul Damasta, în municipalitatea Malevizi din prefectura Heraklion, văzut dintre tufe de grozamă înflorită, cu munți în fundal; stația de conversie nu apare în imagine
Foto: Ziegler175 · CC BY-SA 3.0 · Wikimedia Commons

The electricity interconnection between Crete and Cyprus, rated at 1,000 MW, is expected to be completed at the end of 2031, according to the 2027–2036 Development Programme of Greek transmission system operator ADMIE, as reported by the Greek press on 14 November. The project, valued at €1.94 billion, will connect to Crete at the existing Damasta converter station in the Heraklion prefecture, which is to be expanded.

Progress. According to ADMIE, the contract for the cable section has been signed and the cable is under construction. A preferred bidder has been selected for the converter stations; a new station will be built in Cyprus. Seabed surveys are 60% complete, carried out by the French vessel Abeille Marengo under permits requested and issued by Greece and Cyprus.

The figures. The subsea route is 898 km long and water depth reaches 3,000 m, the project's main technical challenge, according to the same sources. The European Union is contributing €657 million through the Connecting Europe Facility (CEF), as the project has Project of Common Interest (PCI) status.

Impact on prices. A study by the Aristotle University of Thessaloniki, presented at a conference of the Institute of Energy for South-East Europe (IENE), estimates a consumer benefit of €123–138 million a year. The wholesale price in Cyprus is expected to fall by €21.5/MWh, or about 19%, moving closer to the Greek level, while in Greece the effect would range from −0.2% to +0.1%.

What comes next. The Crete–Cyprus link is the first leg of a wider plan in the Eastern Mediterranean: for the 310 km section between Cyprus and Israel, the feasibility study has been completed with positive results. Cyprus is the last EU member state without an electricity connection to the European grid.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page