Grid5 Nov 2026

Elektroprenos BiH modernises its telecoms: BAM 46.7 million for five firms from Bosnia and Serbia

The company that owns Bosnia and Herzegovina's electricity transmission grid has awarded a group of five firms from BiH and Serbia a contract estimated at BAM 46.7 million, about EUR 23.9 million, to modernise its telecommunications system. The existing infrastructure has not been upgraded since 2004, and the turnkey works will take 36 months.

EuroEnergy Newsroom · Bosnia and Herzegovina · 2 min read

Stâlp de înaltă tensiune și linii electrice deasupra orașului Zenica, acoperit de zăpadă; imagine ilustrativă
Foto: Obsuser · CC BY-SA 4.0 · Wikimedia Commons

Elektroprenos BiH, the company that owns the electricity transmission infrastructure in Bosnia and Herzegovina, has awarded the contract to modernise its telecommunications system to a group of five firms, Balkan Green Energy News reported on 4 November. The estimated value is 46.7 million convertible marks (BAM), or about EUR 23.9 million.

Who will do the work. From Bosnia and Herzegovina, the group includes Artco group from Novo Sarajevo and Saga NFG and Telegroup from Banja Luka; from Serbia, Saga and Telegroup from Belgrade. The tender was launched in February 2025 and received only one bid. The contract was signed on 7 October and officially published on 2 November; the execution period is 36 months, on a turnkey basis.

Why now. According to the tender documentation cited by the outlet, the existing infrastructure has not been upgraded since 2004, creating operational risks, capacity limits and technological obsolescence. The new network is to deliver up to 400G on the main links, protection against cyberattacks, lower maintenance costs and greater flexibility. The works cover all 157 of the company's facilities and include network equipment, video surveillance, access control, IP telephony and monitoring of the optical infrastructure.

Context. The transmission system is operated by the Independent System Operator (NOS BiH), while Elektroprenos, owned 58.9% by the Federation of BiH and 41.1% by Republika Srpska, owns the assets. In June the company secured a EUR 46 million EBRD loan for four shunt reactors with a total of 250 MVAr at the Banja Luka 6, Mostar 4, Tuzla 4 and Višegrad substations. As early as 2022, the EBRD approved a EUR 20.1 million loan for the digitalisation of Elektroprenos' telecommunications, according to Germany's GTAI agency; the sources do not say whether it is financing the contract now awarded.

Investment. At a conference in Tuzla in July, Amir Avdagić said, according to the FENA agency, that Elektroprenos BiH had launched an investment cycle worth more than BAM 150 million and that, before the latest amendments to the public procurement law, appeals delayed projects by 18 to 24 months.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page