Crete: Region asks DEDDIE whether a data centre near Chania, applied for at 20 MW, can be connected
The Region of Crete will ask distribution operator DEDDIE in writing whether the data centre planned at Varypetro, near Chania, can be connected to the grid; the application filed with the Region is for 20 MW. Deputy Regional Governor Nikos Kalogeris has come out against it, and the Regional Council discusses the case on 24 November.
EuroEnergy Newsroom · Greece · 2 min read
The deputy regional governor for Chania, Nikos Kalogeris, met on Friday 20 November with residents of Varypetro and Agyia who oppose a data centre planned in the Varypetro Oasis area near Chania. According to Kriti360, the Region of Crete will send a written query to distribution operator DEDDIE to find out whether the facility can be connected to the grid.
The figures. According to zarpanews, the head of the Development Directorate, Manolikakis, said the application filed with the Region is for 20 MW, plus 20 MW of backup. In its written reply presented to Chania's municipal council, the company Prodea Investments described a first phase with an IT load of 1.2 MW and a 1.8 MVA connection, operating from 2028, with estimated annual consumption of about 9,500 MWh; the licence application covers at most 13 MW and a 20 MVA connection.
The grid. On 10 November, Fotis Kazasis of the Technical Chamber of Greece's West Crete branch cited information from DEDDIE that the existing medium-voltage network cannot currently support the connection at the requested capacity because of the saturated line towards Omalos, zarpanews reported. Kostas Iliakis, president of PPC employees in Chania, linked the problem to the saturated Agyia substation and said a new substation would be possible with policy decisions and funding.
The Region's position. Kalogeris said licensing for this category can be summary, without a full environmental study, and that the Region has asked the company for the project's full specifications. “We consider it risky,” he said, adding that the Region will oppose it in the Regional Council. According to zarpanews, he pledged that the regional services will delay the project “by every legal and ethical means”. The residents' spokesperson, Maria Giatroudaki, said Crete's peak demand in the tourist season is 750–800 MW.
What comes next. The Regional Council of Crete meets on Tuesday 24 November in Heraklion, where residents plan to turn out in large numbers. Chania's municipal council voted unanimously against the project, and residents have decided to set up an association and have entrusted the case to two lawyers with the aim of having the project annulled, Agonas tis Kritis reports.