Utilitas: 225 GWh in the third quarter, 94% renewable; 110 MW heat pump plant in Tallinn starts up
Estonian energy group Utilitas produced 225 GWh of energy in the third quarter, 94% of it from renewable sources, and the share of imported fuels is set to fall below 10% next year. The 110 MW heat pump plant in Paljassaare, which uses wastewater and seawater, has delivered its first heat to Tallinn's network.
EuroEnergy Newsroom · Estonia · 2 min read
Utilitas, the Estonian energy group that produces heat for Tallinn's district heating network and electricity from renewable sources, said on 20 November that it produced 225 GWh of energy in the third quarter, 94% of it from renewable sources. Heat accounted for 56% of output and electricity for 42%, with the remainder made up of district cooling and green hydrogen.
The figures. In the third quarter of 2025 the company reported 243 GWh, also 94% renewable, so this year's output is about 7% lower. In the second quarter of 2026 the group's companies in Estonia and Latvia produced 399 GWh, 92% of it from renewable sources.
Gas. “The price of natural gas has risen more than 2.5 times compared to last year, but due to its minimal use, such a price increase will not be passed on to our district heating prices,” said group CEO Priit Koit. He said that as a result of the investments, the share of imported fuels in the production portfolio will fall below 10% next year.
Paljassaare. Gas use will be cut this season by the Paljassaare heat pump plant, which uses treated wastewater and seawater and supplied heat to the network for the first time at the beginning of November. The plant is in its start-up phase, with various tests under way, and will be integrated into Tallinn's district heating system within the next two months. Its four large heat pumps total 110 MW and, according to the company, will cover about a fifth of the annual heat consumption of Tallinn's network, cutting CO₂ emissions by around 100,000 tonnes a year. The investment is close to €100 million. This winter, the Tallinn portfolio is also adding two thermal storage units and electric boilers.
What comes next. In Latvia, Utilitas began building a hybrid park near the village of Lode in Valmiera municipality in August: 117 MW of wind with 18 Vestas turbines of 6.5 MW each and batteries of 60 MW and 240 MWh. The park is due to produce about 330 GWh a year from 2028, equivalent to the consumption of more than 110,000 households.
Real-time data for the country is on the country page
More news
Comments
Be the first to comment.
