Andorra's national electricity company FEDA plans €180–200 million of investment over the next five years, its director Sílvia Calvó told Altaveu. The interconnection with Spain would cost around €70 million, and the Maià wind farm, estimated at €25–30 million, could start construction in the spring.
EuroEnergy Newsroom · Andorra · 2 min read
FEDA, Andorra's public electricity company, plans investments of between €180 million and €200 million over the next five years, director general Sílvia Calvó said in an interview published on Sunday by Altaveu. The money goes mainly to the new interconnection with Spain, the Maià wind farm and possibly a hydropower plant at L'Hospitalet, in France.
The line to Spain. Work has begun on the receiving station on the Runer river, and Endesa is working on the Adrall substation, Calvó said; the aim is to finish in 2029, and the total cost, line and station, would reach around €70 million. The Spanish-Andorran convention for the 220 kV line, in force since 23 September 2026, provides that the investment on Spanish territory is borne entirely by Andorra, through FEDA, according to the text published in the Boletín Oficial del Estado. Together with the link to France, the new connection would allow consumption to double or triple, according to the director.
Domestic generation. The Maià wind farm, estimated at €25–30 million, would cover 7–8% of the country's demand and help Andorra reach the 33% target set by law for 2030, Calvó says. FEDA expects the government to transfer the land by the end of the year so that work can begin in the spring; construction would take about two years because of the altitude. The L'Hospitalet project, with EDF and the French water authorities, could operate from 2032, with a decision once the preliminary design is completed in mid-2027.
Prices and tariffs. FEDA buys around 70% of its energy from Spain and just over 50% from France at fixed prices, which softens this autumn's price rises, according to Calvó. The company requested a 3.1% tariff increase for 2027 in the budget; the board decides in December and the government validates. The director argues that Andorran tariffs are 40–60% below those in Spain and France.
What comes next. Separately, FEDA Ecoterm is studying adding a biomass boiler to the liquefied-gas cogeneration plant in Soldeu, which supplies the local district heating network, Altaveu also reported on 20 November.