Schipkau's 365-metre wind turbine, with its hub at 300 m, is on the grid: a 3.8 MW prototype funded by SPRIND
The 365-metre wind turbine built by Gicon in Schipkau, Brandenburg, with its hub at 300 metres, was connected to the grid on Thursday and is producing electricity. The 3.8 MW prototype cost around 25 million euros, and Gicon says it holds letters of intent for 100 installations in Germany.
EuroEnergy Newsroom · Germany · 2 min read
The 365-metre wind turbine in Schipkau, in Lusatia (state of Brandenburg), was connected to the grid on Thursday, 19 November, and is producing electricity, according to the Dresden company Gicon, which designed it. With its rotor hub at 300 metres, the installation is, according to the company and the German Wind Energy Association BWE, the tallest wind turbine in the world; Gicon notes that in Germany only the Berlin TV tower is three metres taller.
The figures. The prototype has a capacity of 3.8 MW and cost around 25 million euros, according to Gicon. The steel lattice tower weighs 2,000 tonnes and has 22,000 parts, with a telescopic tower inside that can be extended. The installation was commissioned and funded by the Federal Agency for Breakthrough Innovation (SPRIND). Gicon says that, with the same rotor diameter, the turbine produces twice as much energy as a conventional one, because the wind at this height is stronger and steadier; long-term results have yet to be measured.
What comes next. Gicon's managing director, Jochen Großmann, announced five more towers of this type and said there are letters of intent for 100 installations in Germany. The company estimates that up to 4,000 such towers could be added to existing wind farms over the next 15 years and wants series production by 2030 at the latest, with turbines of more than 7 MW. "What matters now is to use the experience from the first installation for the next steps," said SPRIND director Rafael Laguna de la Vera.
Reservations. Economist Felix Müsgens of the Brandenburg University of Technology in Cottbus told tagesschau that the prototype is "still too expensive" and that costs must fall significantly for series production. BWE president Bärbel Heidebroek noted that such a structure requires more material and that maintenance at this height is more demanding.
Context. Max Bögl and Vestas announced on 20 November that a 7.2 MW series turbine with a hub height of 199 metres and a total height of 285 metres is operating near Sengenthal, in Bavaria. Wind supplied around 27% of Germany's electricity generation in 2025, according to the economy ministry, cited by dpa.