Wind22 Nov 2026

Schipkau's 365-metre wind turbine, with its hub at 300 m, is on the grid: a 3.8 MW prototype funded by SPRIND

The 365-metre wind turbine built by Gicon in Schipkau, Brandenburg, with its hub at 300 metres, was connected to the grid on Thursday and is producing electricity. The 3.8 MW prototype cost around 25 million euros, and Gicon says it holds letters of intent for 100 installations in Germany.

EuroEnergy Newsroom · Germany · 2 min read

Turnul cu zăbrele de 365 de metri al turbinei Gicon de la Schipkau, mult peste turbinele obișnuite din parcul eolian din jur; fotografie din 27 octombrie 2026, cu contrastul cerului accentuat
Foto: Osidor · CC0 · Wikimedia Commons

The 365-metre wind turbine in Schipkau, in Lusatia (state of Brandenburg), was connected to the grid on Thursday, 19 November, and is producing electricity, according to the Dresden company Gicon, which designed it. With its rotor hub at 300 metres, the installation is, according to the company and the German Wind Energy Association BWE, the tallest wind turbine in the world; Gicon notes that in Germany only the Berlin TV tower is three metres taller.

The figures. The prototype has a capacity of 3.8 MW and cost around 25 million euros, according to Gicon. The steel lattice tower weighs 2,000 tonnes and has 22,000 parts, with a telescopic tower inside that can be extended. The installation was commissioned and funded by the Federal Agency for Breakthrough Innovation (SPRIND). Gicon says that, with the same rotor diameter, the turbine produces twice as much energy as a conventional one, because the wind at this height is stronger and steadier; long-term results have yet to be measured.

What comes next. Gicon's managing director, Jochen Großmann, announced five more towers of this type and said there are letters of intent for 100 installations in Germany. The company estimates that up to 4,000 such towers could be added to existing wind farms over the next 15 years and wants series production by 2030 at the latest, with turbines of more than 7 MW. "What matters now is to use the experience from the first installation for the next steps," said SPRIND director Rafael Laguna de la Vera.

Reservations. Economist Felix Müsgens of the Brandenburg University of Technology in Cottbus told tagesschau that the prototype is "still too expensive" and that costs must fall significantly for series production. BWE president Bärbel Heidebroek noted that such a structure requires more material and that maintenance at this height is more demanding.

Context. Max Bögl and Vestas announced on 20 November that a 7.2 MW series turbine with a hub height of 199 metres and a total height of 285 metres is operating near Sengenthal, in Bavaria. Wind supplied around 27% of Germany's electricity generation in 2025, according to the economy ministry, cited by dpa.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page