Absheron: Baku parliament ratifies agreement extending the gas field's production period to 40 years, until 2057
Azerbaijan's parliament, the Milli Majlis, ratified on 24 November, in a single reading, the amended production sharing agreement for the offshore Absheron block. The development and production period, which began on 1 March 2017, rises from 30 to 40 years, until 2057, in step with the full development of the field.
EuroEnergy Newsroom · Azerbaijan · 2 min read
Azerbaijan's parliament, the Milli Majlis, adopted on 24 November, in a single reading, the law ratifying the “amended and restated” agreement on exploration, development and production sharing for the Absheron block in the Azerbaijani sector of the Caspian Sea, the agencies Report and Trend and the outlet Azernews reported. The parties are SOCAR, TotalEnergies EP Absheron B.V., SOCAR Absheron and ADNOC International ProjectCo 1 RSC Limited (XRG).
What changes. The main amendment extends the development and production period, which began on 1 March 2017, from 30 to 40 years, so that the contract term now runs to 2057, according to Trend and Azernews. The extension is tied to an additional well, which is expected to sustain gas production until 2057, raise the block's overall gas recovery factor and allow investments to be recovered. The costs of facilities built and financed by the contractors to connect gas and condensate to transport infrastructure become recoverable costs, and the six annexes are consolidated into a single document.
Timeline. The original agreement was signed on 27 February 2009, and the first well started production on 3 July 2023. The final investment decision on the full field development was taken at the end of September 2026, and the amended agreement was signed on 26 September, according to Trend.
Project figures. The full development includes four subsea wells connected by a subsea pipeline to a new, fully electrified onshore processing plant, with start-up in 2029, World Oil reported at the time of the investment decision. Output is set to rise to 6 billion m³ of gas a year and 47,000 barrels of condensate a day, from 1.5 billion m³ and 12,000 barrels a day in the first phase. TotalEnergies (operator) and SOCAR hold 35% each, and XRG 30%. The gas is intended for Azerbaijan's domestic market and for export to Türkiye through existing infrastructure.