Vattenfall reapplies for a permit for Juktan, a 320 MW pumped-storage plant in northern Sweden
On 19 November Vattenfall filed a renewed environmental permit application with the Land and Environment Court in Umeå for the Juktan pumped-storage plant on the upper Umeälven river. With 320 MW, the plant could generate at that output for four days and would enter operation in the mid-2030s.
EuroEnergy Newsroom · Sweden · 1 min read
State-owned energy group Vattenfall announced on 19 November that it has filed a renewed environmental permit application to convert the Juktan power station in Sorsele municipality (Västerbotten County) into a pumped-storage hydropower plant. The application was submitted to the Land and Environment Court in Umeå. The facility would store energy by pumping water up into a reservoir and generate electricity when it is needed.
The figures. Juktan would have an output of 320 MW and could run at that output for four days. Vattenfall describes it as one of Sweden’s largest “batteries”, comparable to the batteries of about 300,000 electric cars. The project includes a new turbine, generator and transformer, as well as a 400 kV outdoor switchyard. “With its 320 MW, Juktan can become an important addition of regulating power in the Swedish electricity system,” said Lovisa Fricot Norén, CEO of Vattenfall Vattenkraft AB.
Background. Commissioned in 1978, Juktan was Sweden’s first large pumped-storage plant and moved water between the lakes Storjuktan, Blaiksjön and Storuman; in 1996 it was converted into a conventional hydropower plant, according to Vattenfall. In February 2025 the Umeå court had rejected the company’s first application, finding it too unclear to be examined, Swedish media reported.
What comes next. If the permit is granted and an investment decision is taken, Vattenfall expects operation to start in the mid-2030s. The company has four hydropower expansion projects under way – Juktan, Harsprånget, Messaure and Porjus – and plans SEK 10 billion of maintenance and replacement investments in its hydropower plants through 2030; growth projects could add about SEK 2 billion. Hydropower provides around 40% of Sweden’s electricity production.