Solar19 Nov 2026

bp: equipment for the 240 MW Shafag solar plant is on site; first phase targeted for mid-2027

Procurement of equipment for the Shafag solar power plant in Jabrayil district has largely been completed, and panels and converters have been delivered to the site, bp's Vice President for the Caspian, Central Asia and Türkiye region said on 19 November. Work is continuing with the goal of finishing the first phase by the middle of next year.

EuroEnergy Newsroom · Azerbaijan · 2 min read

Rânduri de panouri solare și o stație electrică la centrala solară Garadagh de lângă Baku, văzute de sus; imagine ilustrativă
Foto: Press Service of the President of the Republic of Azerbaijan · CC BY 4.0 · Wikimedia Commons

Procurement of the equipment needed for the Shafag solar power plant, under construction in Azerbaijan's Jabrayil district, has largely been completed, and construction is progressing as planned, bp's Vice President for the Caspian, Central Asia and Türkiye region told journalists on 19 November, according to the APA news agency. Solar panels, converters and other equipment have been purchased and delivered to the site.

Progress. In one section of the site, pile installation, panel placement and mechanical work have been completed; mainly electrical installation remains there. In another section, mechanical work is continuing. The bp official said certain logistical difficulties, as well as equipment transport and supply, could affect the schedule, but no serious problems are currently being observed. Azerenerji has completed preparations for the project's substation. Asked whether the first phase would be completed by the middle of next year, he said work was continuing toward that goal.

The numbers. Shafag has a capacity of 240 MW and is expected to generate about 500 million kWh a year, according to pv magazine. The project belongs to Shafag (Jabrayil) Solar Limited, in which bp holds 50.01%, SOCAR 39.99% and Azerbaijan Investment Company 10%. Under a virtual power transfer mechanism, the electricity goes into the Jabrayil grid, and the operator delivers an equivalent amount to the Sangachal terminal so that it can cover its consumption with renewable energy.

The grid. In August, Azerenerji commissioned the 220/110/10 kV Yeni Sangachal substation, which integrates the plant into the national system and supplies bp's Sangachal terminal; the substation is connected to the grid by four new 220 kV lines with a combined length of 111 km, Power Line reported.

Context. On 18 November, Azerbaijan's energy minister met bp's regional president. According to Report, they discussed oil, gas and green energy projects, electricity interconnections between Europe and Asia, and prospects for supplying electricity to bp's production facilities.

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page