Türkiye: first YEKA floating solar plant, 35 MW, to start producing in 2027 on the Demirköprü dam
The floating photovoltaic plant on the Demirköprü dam, in the Salihli district of Manisa province, will deliver its first 9 MW between late January and mid-February 2027 and full capacity by the end of May, the investor told Anadolu. The €41 million project has 91,368 panels and 50.25 MWp.
EuroEnergy Newsroom · Türkiye · 2 min read
Türkiye's first floating solar plant awarded under the YEKA mechanism (Renewable Energy Resource Areas) will begin generating electricity early next year on the reservoir of the Demirköprü dam, in the Salihli district of Manisa province, the Anadolu news agency reported on 24 November. Installation on the water began in October, when the first panels were lowered onto the lake.
The figures. The plant covers about 500 decares (roughly 50 hectares) of water surface and uses 91,368 panels of 550 W each, with total capacity of 50.25 MWp and grid connection capacity of 35 MW. Expected annual output is about 77.6 million kWh, and total investment is estimated at €41 million. The floating system will weigh 8,000 tonnes in total.
The timeline. The pre-licence was granted on 23 July, and site work began three months ago. Muhammet Balkaya, chairman of the investor company, told Anadolu that the first 9 MW will start producing between late January and mid-February 2027, and the whole plant by the end of May. He said the capacity could meet the needs of about 20,000 households.
Context. The reservoir of the 69 MW Demirköprü hydropower plant, owned by state-run EÜAŞ, was proposed by the Energy Ministry as the first site for a floating solar auction, Balkan Green Energy News reported. At the YEKA auction of 25 November 2025, the Demirköprü Yüzer GES group, owned equally by Arya Yenilenebilir Enerji and PMS Polietilen Mamulleri, won with 3.25 euro cents/kWh and a contribution of €225,000 per MW, according to Para magazine. The reservoir's water level can vary by more than 34 metres within a year, Haberler.com noted, so the platforms, moorings and cables were designed for changing levels.
What comes next. Wind, water level and platform movements will be monitored remotely. The environmental impact assessment report has been approved by the Ministry of Environment, Urbanisation and Climate Change, and fish populations and environmental indicators will be tracked through water samples during construction and operation.
The country's real-time data are on the country page
More news
Comments
Be the first to comment.
