Minsk's 1,035 MW TEC-4 combined heat and power plant completes tests of new 110 kV switchgear; upgrade runs to 2027
Acceptance tests of a 110 kV gas-insulated switchgear using SF6 were completed on 21 November at the TEC-4 combined heat and power plant in Minsk, state-owned company Minskenergo said. The new equipment replaces old oil-filled apparatus and opens the modernisation of the plant's 110 kV outdoor switchyard, due to be completed in December 2027.
EuroEnergy Newsroom · Belarus · 1 min read
Acceptance tests of the new gas-insulated switchgear (KRUE 110 kV) at the TEC-4 combined heat and power plant in Minsk were completed on 21 November, state enterprise Minskenergo said, as quoted by the BelTA news agency and the daily SB. Belarus Segodnya.
What has changed. During the reconstruction, physically worn and obsolete oil-filled equipment, as well as relay protection and automation devices based on electromechanical relays, were replaced with modern, highly reliable equipment, according to the company.
The figures. For 72 hours, Minskenergo specialists continuously monitored the equipment's operation, and the stability and correctness of its parameters were fully confirmed, the statement said. TEC-4, commissioned in 1977, has an installed electrical capacity of 1,035 MW and a heat capacity of 1,656.6 Gcal/h; it runs on natural gas, with fuel oil as a back-up fuel, according to the plant's entry on Russian-language Wikipedia, which cites Minskenergo data.
Context. The plant, located in the capital's western industrial zone, supplies about 45.6% of the heat delivered to Minsk and roughly one tenth of Belarus's annual electricity output, according to the same source. The plant's outdoor switchyards operate at 110 and 330 kV. It is the main source of heat for heating, ventilation and hot water in the western, south-western and partly the northern and central parts of the city.
What comes next. Minskenergo says commissioning of the KRUE 110 kV marks the start of a major stage in the modernisation of the 110 kV outdoor switchyard (ORU-110 kV), which will be completed in December 2027 and will increase the reliability of electricity supply to Minsk and the Minsk region.