Sweden awards first Kraftlyftet grants: SEK 1.1 billion for around 100 MW of new capacity in the south
The Swedish Energy Agency (Energimyndigheten) announced on 23 November the first decisions under the Kraftlyftet programme: six energy companies will receive a combined SEK 1.1 billion for biomass-fired combined heat and power and for hydropower plants. The projects could add around 100 MW of new capacity in the SE3 and SE4 price zones.
EuroEnergy Newsroom · Sweden · 2 min read · updated 25 Nov 2026
Energimyndigheten, the Swedish Energy Agency, announced on Monday, 23 November, the first funding decisions under Kraftlyftet, the state programme supporting investment in electricity generation and storage. Six companies – Fortum, Locus Hydro, E.ON Energiinfrastruktur, Karlskoga Kraftvärmeverk, Vattenfall Värme and Mälarenergi Vattenkraft – will together receive SEK 1.1 billion for biomass-fired combined heat and power plants and for hydropower plants.
What was decided. According to the list published by the agency, the money goes to 11 projects. The largest amounts go to E.ON's new combined heat and power plant at Energihamnen in Malmö (around SEK 322.3 million, in zone SE4), to a new biomass-fired CHP plant by Karlskoga Kraftvärmeverk, designed for the defence industry and energy preparedness (320 million), and to the conversion of Vattenfall Värme's Carpe Futurum heating plant into a biomass-fired CHP plant (around 219 million). The rest funds the modernisation or replacement of eight small hydropower plants owned by Fortum, Locus Hydro and Mälarenergi.
The figures. The agency received around 400 applications, with a total requested amount of more than SEK 13 billion. The projects approved now could add around 100 MW of generating capacity in SE3 and SE4, equal to the consumption of the inhabitants of a medium-sized Swedish town, according to Energimyndigheten. Aid can cover up to 45% of the investment (30% for storage and for CHP that does not run entirely on renewable fuel), capped at 30 million euros per project.
Context. “Southern Sweden has long had a deficit of local electricity generation,” said the agency's director general, Caroline Asserup. One of the recipients, Mälarenergi Vattenkraft, receives around SEK 60 million for a new hydropower plant on the Kolbäcksån river in Surahammar, where the current station dates from 1927. According to the company, the plant currently produces 4.6 GWh a year, and its capacity will double from 1 MW to 2 MW.
What comes next. The 1.1 billion are the first decisions in the call for generation and storage, through which a total of SEK 4.2 billion is to be distributed. The agency is continuing to assess the remaining applications and will take further decisions up to the first half of 2027. The supported projects must be completed by 31 December 2031 at the latest.