Statkraft builds 57.7 MWp Kilcush solar farm in Offaly: Ireland's first wind, solar and battery project
Statkraft has entered the final stage of its Cushaling project in County Offaly, which will combine wind, solar and battery storage on one site, a first in Ireland. The company warns, however, that current rules do not allow it to operate as an integrated hybrid project.
EuroEnergy Newsroom · Ireland · 2 min read
Norwegian company Statkraft is building the 57.7 MWp Kilcush solar farm southwest of Edenderry, County Offaly, the final stage of its Cushaling development, the first project in Ireland to bring wind, solar and battery storage together on one site, according to reNEWS and the Offaly Independent.
The figures. Construction began in May 2026; energisation is targeted for April 2027, with commercial operations expected by the end of that year. The solar farm covers about 90 hectares and is expected to power around 20,000 homes, the Offaly Independent reports. The Cushaling site already includes a 55.8 MW wind farm and a 22.8 MW, four-hour battery system, launched in February as the first of its kind in Ireland, according to RTÉ.
The obstacle. Statkraft says current regulatory and system operator arrangements prevent the development from operating as a fully integrated hybrid project. Hybridisation would allow the wind and solar farms to charge the battery when the grid cannot take all the output, and the battery to discharge when wind and sun are weaker, reducing the need for imported gas.
The analysis. Analysis by Cornwall Insight cited by reNEWS shows that an unrestricted hybrid scenario could make an additional 1,200 GWh of renewable electricity usable each year and cut renewable dispatch-down by 16%. Potential savings would be €146m a year across the island's Single Electricity Market (SEM), with 2,522 GWh of gas generation avoided and 461,000 tonnes less CO2.
What the company wants. “Now, over 15% of renewable power generated in Ireland is wasted,” said Kevin O’Donovan, Statkraft's senior vice president and country manager for Ireland and the UK. The company wants EirGrid and the regulator, the CRU, to complete within the next 12 months the changes allowing grid capacity sharing, direct wires and hybridisation.
Real-time data for the country is on the country page