Spain approves its electricity grid plan to 2030: €17,142 million and 47 GW of new demand
On 20 November the Council of Ministers approved the binding plan for the electricity transmission grid to 2030, with investment of €17,142 million. The plan includes 6,707 km of new lines and allows 47 GW of new demand to connect, from industry and hydrogen to data centres and housing.
EuroEnergy Newsroom · Spain · 2 min read
The Spanish government on Friday, 20 November, approved the 2030 Electricity Planning, the binding document that sets out which transmission lines, substations and interconnections will be built by the end of the decade. According to the Ministry for the Ecological Transition (MITECO), total investment amounts to €17,142 million.
The figures. Of the total, €15,133 million goes to reinforcing the national transmission grid and €2,010 million to international interconnections. The plan includes 6,707 km of new lines, the upgrading of 8,164 km of existing lines and 193 substation sites. According to Red Eléctrica calculations cited by the ministry, savings for the system would exceed €3,593 million a year.
New demand. The grid will be able to take 47 GW of new consumption, compared with 2 GW in the current plan, which runs to 2026. Minister Sara Aagesen presented the breakdown in Congress on 12 November: 14.9 GW for industry, 12.4 GW for renewable hydrogen and derivatives, 9.3 GW for data centres, 6 GW for housing and territorial development – around three million highly electrified homes –, 2.5 GW for transport, 1.8 GW for ports and 0.5 GW for rail.
Context. The initial proposal envisaged €13,590 million and 27 GW of demand; the figures rose after the analysis of the 2,566 submissions received in the public consultation, according to Xataka. The final investment is almost 150% higher than in the previous plan. According to El Periódico de la Energía, Aagesen described the plan as built from the bottom up and discussed with the regions. In July the government approved a decree allowing an additional €17,900 million of investment in transmission and distribution grids.
What comes next. The planning is binding and derives from the scenario of the National Integrated Energy and Climate Plan (PNIEC) 2023–2030. At the same meeting, the cabinet also approved a decree that speeds up grid access and connection procedures for renewables and improves the information on gas bills.