France: nuclear authority asks EDF for proof of its new soil-reinforcement solution for the Gravelines EPR2 reactors
France's nuclear safety and radiation protection authority (ASNR) considers the new solution proposed by EDF for the soft ground at Gravelines, where two EPR2 reactors are to be built, “notably simpler”, but wants detailed studies to demonstrate its performance. EDF must submit a consolidated study programme with a detailed schedule by the end of January 2027.
EuroEnergy Newsroom · France · 2 min read
France's Nuclear Safety and Radiation Protection Authority (ASNR) announced on 20 November that it had identified “no a priori obstacle” to the further development of the new soil-reinforcement solution proposed by EDF for the two EPR2 reactors planned at Gravelines, in the north of the country, but that its performance still has to be demonstrated through detailed studies. The position is set out in a letter to EDF dated 19 November and in an expert opinion of 30 October.
What has changed. The Gravelines site has soft soil over a great thickness, and the EPR2 reactors are very heavy, so the ground has to be reinforced before construction to limit settlement and guard against the risk of liquefaction during an earthquake. EDF's first solution, presented in 2024, combined “soil-mixing” cells (soil mechanically mixed with a cement-based binder) with rigid inclusions under the heaviest buildings. In March 2026, EDF presented a new variant: excavating the first layer of soil under the power block and replacing it with fill, beneath which rigid inclusions are installed, that is, vertical reinforced-concrete columns that transfer the loads to stronger layers. The ASNR considers dropping the soil-mixing cells “a notable simplification”.
What the authority is asking for. The ASNR is asking EDF to send, before the end of January 2027, the consolidated programme of design studies together with a detailed schedule, so that the review can be completed before construction steps make it difficult to change the solution. The authority wants further work on the validity of the numerical models, on the propagation of seismic motion through the reinforced soil and on the method used to check the seismic bearing capacity. EDF has committed to installing, from the start of earthworks, sensors to monitor soil deformation and pore water pressure.
Context. By a decree of 20 August 2026, the government authorised site preparation work at Gravelines, where six 910 MW reactors are already operating, according to World Nuclear News. Gravelines is one of the three sites for the first six EPR2 reactors, together with Penly and Bugey; the first reactor at Penly is expected around 2038, according to AFP. EDF said it is continuing its work and will provide the requested information.