Signet Banka lends €9.1 million for a 15 MWp solar park with 40 MWh of batteries near Jūrmala
Signet Banka has granted €9.1 million to Jūrmalas SES for a hybrid park with 15 MWp of solar panels and a 40 MWh battery system, being built alongside the railway between Riga and Jūrmala. Commissioning is scheduled for November 2026, according to the bank.
EuroEnergy Newsroom · Latvia · 2 min read
Signet Banka has granted €9.1 million in financing to SIA Jūrmalas SES for the construction of a solar power plant with a battery energy storage system (BESS) alongside the railway on the stretch between Riga and Jūrmala, the bank announced on 2 November. The project developer is the Latvian company Aretis Group.
The figures. The park covers 23 hectares, where almost 21,000 solar panels with a total capacity of 15 MWp have been installed, together with a battery system with a capacity of 40 MWh. The plant is expected to generate around 16,300 MWh a year, equivalent to the average annual consumption of about 7,600 Latvian households, according to the bank. The electricity will be fed into the public grid and will help cover the consumption of the city of Jūrmala. The site is in Babīte parish, Mārupe municipality, in an area earmarked for future commercial development.
The role of the batteries. Combining solar generation with storage allows the electricity to be stored and released into the grid at times of higher demand. The battery system will also be able to take part in the balancing and frequency regulation markets, providing services to transmission system operator Augstsprieguma tīkls (AST), Dienas Bizness reports. “Energy security today means not only the ability to produce enough electricity, but also the ability to store it, manage it flexibly and ensure the stability of the system,” said Artūrs Plūme, head of Aretis Group.
Background. According to its website, Aretis Group has 143 MWp of photovoltaic projects and 280 MWh of batteries in Latvia in its portfolio, including hybrid parks in Ventspils and Līvāni that were commissioned in March 2026. Nationally, AST announced in October that the capacity of solar and wind plants connected to the transmission grid had passed 1,700 MW; this year the operator has completed connections for seven new solar parks totalling 787 MW and four wind farms totalling 467 MW. AST expects more and more solar plants to be paired with batteries.
What comes next. The hybrid park near Jūrmala is scheduled to be commissioned in November 2026, according to Signet Banka.