Solar16 Nov 2026

Poliex plans a 1 MW solar plant in Berane: 1,820 panels, with public comments open until 17 November

Berane-based Poliex, in northern Montenegro, has asked the local authorities to decide whether its planned 1 MW solar plant with 1,820 panels needs an environmental impact assessment study. The public can send comments to the municipality until 17 November.

EuroEnergy Newsroom · Montenegro · 1 min read

Centrală solară montată pe sol, cu dealuri împădurite în fundal, lângă hidrocentrala Brežice din Slovenia; imagine ilustrativă
Foto: Janezdrilc · CC0 · Wikimedia Commons

The Berane company Poliex is planning a one-megawatt photovoltaic plant in the settlement of Babino, on its own land, according to the daily Vijesti. The project would have 1,820 ground-mounted panels on steel structures, and the nearest house would be about 130 metres away as the crow flies.

What was requested. Poliex has submitted to the Berane municipality's Secretariat for Communal and Housing Affairs, Transport and Environmental Protection a request for the authority to decide whether an environmental impact assessment study is needed. The municipality has invited the public to inspect the documentation and send comments by 17 November 2026.

The figures. The plant would occupy plot 2920 in the Polica cadastral area: the panels would cover 5,654 m² of a 14,535 m² plot. The documentation provides for five inverters of 200 kW each, with the panels connected in strings of 28. The connection would be made via a new underground 10 kV cable, about 2.5 km long, to the existing "Polica" substation; the electricity would be sold to the distribution grid.

Context. The plant would operate only while the distribution grid is energised and would disconnect automatically if voltage is lost, the documentation states. The site lies outside protected areas and belongs to the Lim river basin. The municipality had set the location and urban planning conditions for the plant and the 10 kV cable on 6 August. Poliex, founded in 1983, produces explosives and chemical products, Vijesti writes.

What comes next. Once the public consultation ends, the local authority must decide whether the investor will have to prepare the environmental impact assessment study.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page