North Macedonia prepares to restart the Negotino power plant at an estimated cost of €170–175/MWh
Prime Minister Hristijan Mickoski said the oil-fired Negotino plant is being prepared to generate electricity again and that shipments of Kosovo coal for Bitola and Oslomej will begin. Generation at Negotino would cost €170–175/MWh, while exchange prices reach €400–500/MWh on some days.
EuroEnergy Newsroom · North Macedonia · 1 min read
The oil-fired Negotino thermal power plant, usually kept in cold reserve, is being prepared to generate electricity again, North Macedonia's Prime Minister Hristijan Mickoski said on 21 November in Delčevo, according to the portals 360stepeni and Faktor. The plan is part of a financial model of state-owned utility ESM that also covers the REK Bitola units, the Oslomej plant and the hydropower plants.
The costs. At current fuel oil prices, generation at Negotino would cost €170–175/MWh, while exchange prices reach €400–500/MWh on some days, Mickoski said. The plants would run during expensive hours to cover the losses expected in December and January. "The plan is feasible," the prime minister said.
The fuel oil. ESM has tendered about 45,000 tonnes of fuel oil with an estimated value of €42.6 million including VAT, with bids to be opened on 24 November after the deadline was extended, Faktor reported. The fuel would arrive via the port of Thessaloniki and then by rail. According to broadcaster Telma, Negotino has not operated for about three years.
Coal from Kosovo. In August, ESM and Kosovo's KEK signed a three-year contract for about 3 million tonnes of coal from the Obilić mine at a fixed price of €24.4 per tonne, Balkan Green Energy News reported. The coal is intended for the Bitola and Oslomej plants, and ESM expects about 800 GWh of additional generation a year.
What comes next. Transport would use a new border crossing to Kosovo with about 200 trucks a day, plus 50–60 through Blace, for more than 6,000 tonnes a day, according to Faktor. No date has yet been set for the Negotino restart or for the first deliveries.
Real-time data for the country are on the country page.
More news
Comments
Be the first to comment.
