Ireland's RESS 6 auction delivers over 1,550 MW: 1,367 MW of solar and just 188 MW of onshore wind
The provisional results of the sixth RESS auction, announced on 25 November by Ireland's energy ministry and EirGrid, award support to 28 projects totalling over 1,800 GWh. Solar dominates with 22 projects and 1,367 MW, while onshore wind secures just 188 MW, at a weighted average price of €99.35/MWh.
EuroEnergy Newsroom · Ireland · 2 min read
Ireland's Department of Climate, Energy and the Environment announced on 25 November the provisional results of the sixth auction under the Renewable Electricity Support Scheme (RESS 6). The provisionally successful offers total over 1,800 GWh, equivalent to more than 1,550 MW of new onshore capacity, enough, according to the department, for over 450,000 homes.
The figures. According to the report by EirGrid, the auction administrator, 28 projects were successful: 22 solar projects with 1,367 MW and 6 onshore wind projects with 188 MW. The weighted average price of the successful offers is €99.35/MWh for wind and €102.42/MWh for solar. Of the 63 applications for qualification, 46 projects entered the auction, 4 did not qualify and 13 withdrew; a further 18 offers were provisionally unsuccessful. The projects will contribute at least €2/MWh to community funds, around €56.82m in total over the life of the scheme.
What is new. RESS 6 is the first Irish auction to apply the non-price criteria of the EU Net-Zero Industry Act (NZIA): offers were ranked by a score combining price, resilience and energy system integration, and solar and wind competed in separate pots.
Reactions. Minister Darragh O'Brien acknowledged that “we are not seeing enough onshore wind farms entering these auctions”, with wind outpaced by solar developments. Industry body Solar Ireland welcomed the result but noted that a further 1,014 MW of solar went without a contract; Ireland's target is 8 GW of installed solar by 2030, and almost 3.5 GW is currently in operation, according to the department. Noel Cunniffe, chief executive of Wind Energy Ireland, called for lower auction prices and faster grid connections, which now often take 6–7 years, reNEWS reported.
What comes next. The results are subject to ministerial approval; according to EirGrid's timetable, the final results are scheduled for 9 December 2026.