Kyon Energy begins commissioning its 100 MW, 203 MWh battery at Dahlem, behind the original schedule
Kyon Energy has started technical testing of its 100 MW, 203 MWh battery storage system at Dahlem in North Rhine-Westphalia, after the project's substation was energised in August. Commercial operation, originally planned for October 2026, is now expected shortly.
EuroEnergy Newsroom · Germany · 2 min read
Kyon Energy has begun the technical commissioning of its battery storage system at Dahlem, in the Euskirchen district of North Rhine-Westphalia, with a power of 100 MW and a capacity of 203 MWh, the company announced on 24 November. The project thus moves from construction into testing, and commercial operation is expected “shortly”, according to the press release.
What happened. The two grid connections of the substation built for the project were energised at high voltage in August 2026. In the so-called “hot commissioning” phase, the electrical and control components, their interaction and the grid connection are tested under various operating conditions. “With the start of hot commissioning, the decisive transition from construction to operation begins,” said managing director Thomas Maubert.
The figures. The plant has 70 containers with lithium iron phosphate cells, installed in October 2025 and supplied by the French manufacturer Saft, according to pv magazine. The project page gives a gross capacity of 202.8 MWh and names Westnetz as grid operator. In 2024, Kyon put the investment at more than €75 million.
Context. In December 2025, Kyon and Saft had announced energisation for the second quarter of 2026 and commercial operation for October 2026, so the project is slightly behind schedule; the company did not give a reason, pv magazine notes. Dahlem is the fourth storage system operated by Kyon itself, after Arnsberg, Schobüll and Faid, and is part of a portfolio of 11 projects in Germany in which Allianz Global Investors acquired a 50% stake in 2026. Kyon is part of TotalEnergies Integrated Power Germany.
What comes next. Once testing is complete, the battery will enter commercial operation and will be operated by Kyon. According to the project page, it will provide primary control reserve and be optimised on the spot market.