Kosovo declares 60-day electricity emergency measures; KEK must secure import capacity for December
Kosovo's government on 16 November approved emergency measures for energy supply valid for 60 days: the Ujman hydropower plant will generate at peak times for the universal service supplier, and public institutions must save electricity. KEK has been given a public service obligation to secure cross-border capacity for December.
EuroEnergy Newsroom · Kosovo · 1 min read
Kosovo's government approved at its meeting on 16 November a decision declaring emergency measures for energy supply, valid for 60 days from entry into force, according to the official communiqué of the meeting. Economy Minister Artane Rizvanolli presented the proposal as a response to the "extraordinary circumstances" facing the energy sector, Buletini Ekonomik reports.
What was decided. The decision obliges the Ujman hydropower plant, i.e. the Ibër-Lepenc enterprise, to generate electricity at times of highest demand and sell it to the universal service supplier, for citizens and for micro, small and medium-sized enterprises. All public institutions must take measures to save electricity during this period, and the government may adopt further measures in the coming weeks and months.
Import capacity for December. In a second decision, the Kosovo Energy Corporation (KEK) was given a temporary public service obligation to secure the rights to use cross-border electricity transmission capacity for 1–31 December 2026. According to the government, the measure addresses the lack of planned generation from unit B1 of the Kosova B power plant. The minister described it as a preventive measure to secure in time the capacity needed for trade.
Background. At the same meeting, the government banned electricity trading with companies whose parent company is registered in Serbia, which are branches of companies there or which have links with persons registered in Serbia, except for transactions arising from the 2013 energy agreements. Asked about rising import costs, the minister said the government is making "maximum efforts" to keep supply costs from rising and, if they do rise, will take measures to protect citizens.
What comes next. The emergency measures apply for about two months, while KEK's obligation covers the whole of December.