Kazakhstan: Zhanaozen gas processing plant, 900 million m³ a year, has 65.1% of its key equipment ready
KazMunayGas says that for the new gas processing plant in Zhanaozen, 169 of 240 long-lead equipment items are ready and a third of the planned concrete has been poured on site. The plant, built using a modular method, will process 900 million m³ of natural and associated gas a year for the Mangistau region.
EuroEnergy Newsroom · Kazakhstan · 2 min read
Construction of the new gas processing plant in Zhanaozen, in the Mangistau region of western Kazakhstan, is advancing, national company KazMunayGas (KMG) said on 25 November after a site visit by its management board chairman, Askhat Khassenov. The project is being carried out on the instruction of the head of state, the company said.
The figures. Of 240 long-lead equipment items, 169 are ready and 71 are in progress, and overall manufacturing progress has reached 65.1%, according to KMG. At the end of October the company reported 138 items ready and progress of 61.6%. On site, 20,970 m³ of concrete has been poured, or 33.3% of the planned volume; earthworks, foundations and the assembly of spherical and cylindrical tanks are continuing.
Deliveries. Equipment is being shipped in stages by sea. The first vessel, unloaded at the port of Ersai, brought a flare unit, a thermal oxidiser, an oil heater, heat exchangers and tanks with electric heaters; the second delivered pipe rack structures for the links between the plant's units. Two more ships are on the way, one carrying the plant's key equipment: two Siemens compressor units and two gas turbines. The main process units and modules are being made in China; the modular method, KMG says, shortens the time and volume of assembly work on site.
Context. The plant will have a capacity of 900 million m³ of natural and associated gas a year and will produce sales gas, liquefied petroleum gas and a pentane-hexane fraction for households and industry in the Mangistau region. According to Forbes Kazakhstan, commissioning was originally planned for 2024, then postponed to 2025, and February 2027 had been given as the new deadline for completing construction.
What comes next. KMG says the resources deployed on site are being increased gradually as the work front expands. The 25 November statement gives no commissioning date.