Kainuun Voima to modernise automation at three hydropower plants in Kajaani producing about 100,000 MWh a year

Valmet will supply a new automation system for Kainuun Voima’s Koivukoski II, Koivukoski III and Ämmäkoski hydropower plants on the Kajaaninjoki river. The three plants, with a combined capacity of about 30 MW, will be operated from a single control room from the last quarter of 2027.

EuroEnergy Newsroom · Finland · 2 min read

Hidrocentrala Koivukoski de pe râul Kajaaninjoki, la răsărit, iarna, cu apa aburind între maluri înzăpezite
Foto: Teuvo Salmenjoki · CC BY-SA 4.0 · Wikimedia Commons

Finnish group Valmet will supply the Valmet DNAe automation system for three hydropower plants owned by Kainuun Voima on the Kajaaninjoki river in the town of Kajaani: Koivukoski II, Koivukoski III and Ämmäkoski, Valmet announced on 4 November. The new systems will replace the current automation, supplied by another vendor, as well as part of the electrical systems.

Scope of the contract. The delivery includes hydro turbine automation, automation of the auxiliary installations (BOP) and SCADA functions that allow the three plants to be monitored and controlled from a single control room. The electrical scope comprises new synchronisation equipment at Ämmäkoski and Koivukoski II, upgrades to the protection and excitation systems of the existing generators, a flood protection solution for Ämmäkoski and the modernisation of the medium- and low-voltage systems at Koivukoski III. The work will be integrated into the turbine renovation project.

The figures. According to Valmet, the plants have a combined capacity of about 30 MW and produce around 100,000 MWh a year; Kainuun Voima’s website gives 35 MW for the Kajaaninjoki. The value of the order was not disclosed; it was included in Valmet’s orders received in the third quarter of 2026. The systems are scheduled to enter service in the last quarter of 2027.

Background. Kainuun Voima is owned in equal shares by the town of Kajaani and Kajaanin Energiatuotanto Oy, and the first turbines at Ämmäkoski were installed in 1917. According to the company, Koivukoski III, completed in 1995, has an underground machine hall, delivers power via a 110 kV line connected to the national grid and takes part in frequency regulation when operating. The company is also responsible for the statutory regulation of lake levels in the Sotkamo area.

What comes next. Kainuun Voima managing director Kimmo Keinänen said the new system will bring several separate systems together into a single whole, reducing the number of interfaces and shortening response times for maintenance and service. According to him, the investment is intended to ensure the best possible ability of the automation to meet the requirements of the electricity market.

Real-time data for the country are on the country page.

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page