Italy: Terna publishes the first division of the transmission grid into micro-zones, a first step against “virtual saturation”
Italian transmission system operator Terna on 19 November published the first official division of the national grid into micro-zones, following the methodology approved by the Ministry of Environment and Energy Security. The micro-zones become the reference for connection requests and for calculating the additional capacity the grid can accept.
EuroEnergy Newsroom · Italy · 2 min read
Terna, the operator of Italy’s electricity transmission grid, on the evening of 19 November published for the first time the division of the National Transmission Grid (RTN) into micro-zones, drawn up according to the methodology approved by the Ministry of Environment and Energy Security (MASE). The map can be consulted on the operator’s TE.R.R.A. portal, according to QualEnergia and Staffetta Quotidiana.
What was decided. The step implements Article 3 of MASE decree no. 291 of 8 September 2026, adopted under decree-law no. 21/2026, the so-called “Bollette decree”. Micro-zones are portions of the grid within the market zones, of regional or sub-regional size, and will be the territorial reference for handling connection requests and for calculating the additional capacity the system can integrate, Nextville notes. Quotidiano Energia describes the publication as the first step of the new “open season” mechanism.
The problem. The decree targets so-called virtual saturation: connection requests for renewable projects that reserve capacity on paper even though many are never authorised, causing delays and bottlenecks. According to Econnextion platform data cited by Milano Finanza, as of 31 July 2026 requests to connect to the transmission grid totalled about 314.2 GW for renewable plants and 289.7 GW for storage, more than 603 GW in all.
How it works. Under the decree, Terna publishes and updates at least quarterly the maximum additional capacity available for renewables and storage on each portion of the grid, with offshore plants excluded. Micro-zone capacity and the offer of connection solutions are published at least 30 days before an “open season” opens, and the methodology, perimeter and number of micro-zones are reviewed at least every two years. When the decree was signed, minister Gilberto Pichetto Fratin said grid capacity would be “public, updated quarterly and managed according to objective and non-discriminatory criteria”.
What comes next. Once operational, the system should free up capacity blocked by requests that no longer correspond to buildable projects, according to Nextville. According to Milano Finanza, an operator that accepts a connection solution has 90 days to file for authorisation, and capacity is reserved permanently only once the permit is obtained.
Real-time data for the country are on the country page.