Italy: Terna awards all 16 GWh of storage in the second MACSE auction at €11,382/MWh-year, 12% lower

The second MACSE auction, concluded by Terna on 24 November, awarded 16 GWh of lithium-ion batteries in the South and the islands, the entire requirement, at a weighted average price of €11,382/MWh-year. The price is about 12% below the first auction, and the plants are due to enter service in 2029.

EuroEnergy Newsroom · Italy · 1 min read

Containere de baterii litiu-ion aliniate la sistemul de stocare Sunlight Storage II, din California; imagine ilustrativă
Foto: Bureau of Land Management California · Public domain · Wikimedia Commons

Italian transmission system operator Terna concluded on 24 November the second auction of MACSE, the mechanism through which new electricity storage capacity is contracted, this time for delivery in 2029. The procedure awarded 16 GWh of storage capacity in the South and the islands, 100% of the required amount, according to results reported by ANSA, Teleborsa and Affaritaliani.

The figures. The weighted average award price was €11,382/MWh-year, well below the reserve premium of €27,000/MWh-year and about 12% lower than in the MACSE auction for 2028. Around 67 GWh of new projects qualified, and about 43 GWh were offered in the auction, almost three times the requirement. Only lithium-ion battery systems were eligible.

By zone. Of the 16 GWh, 2.8 GWh go to the Centre-South zone at an average price of €10,716/MWh-year; 9.6 GWh to the South and Calabria at €11,575/MWh-year; 3 GWh to Sicily at €11,467/MWh-year; and about 0.5 GWh to Sardinia at €10,925/MWh-year. QualEnergia notes that prices fell in every zone, especially in the islands and the Centre-South.

Background. The first MACSE auction, held on 30 September 2025, awarded 10 GWh for delivery in 2028 at a weighted average price of €12,959/MWh-year. The quantity for 2029 was approved by the Ministry of the Environment and Energy Security (MASE) after an opinion from the regulator ARERA. The methodology sets the volume so that the marginal cost of new storage stays below the benefit of lower gas-fired generation costs.

What comes next. The plants contracted in this second auction are expected to enter service during 2029, according to Terna.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page