Gabčíkovo hydropower plant gets another €30 million to renew two turbine-generators

State enterprise Vodohospodárska výstavba has secured a second €30 million grant from the Environmental Fund, using Modernisation Fund money, for the Gabčíkovo hydropower plant. The funds go to renewing turbine-generators TG1 and TG2, part of a plant modernisation worth more than €465 million.

EuroEnergy Newsroom · Slovakia · 2 min read

Complexul hidrotehnic Gabčíkovo de pe Dunăre: intrarea în ecluză și turnul de comandă, văzute de pe o navă
Foto: HaSt · CC BY-SA 4.0 · Wikimedia Commons

The Gabčíkovo hydropower plant on the Danube is getting fresh support for its modernisation. State enterprise Vodohospodárska výstavba (VVB) has obtained €30 million from the Environmental Fund (Environmentálny fond), financed by the Modernisation Fund, the SITA news agency reported on 6 November. It is the second grant of this kind for the plant.

What is funded. The money is intended to renew the mechanical and electrical parts of two turbine-generator units, TG1 and TG2. According to VVB, the aims are better technical condition and operational safety, higher efficiency of electricity generation and the ability to pass more water through the turbines at high flows, which helps flood management. The project also reduces the amount of oil in hydraulic systems and of SF₆ insulating gas in electrical equipment.

The figures. The full modernisation of the plant costs more than €465 million and includes eight new Kaplan turbines, eight generator stators and five block transformers, according to SITA; the grant covers only the two-unit project. The winning bid in the international tender, submitted by the ANDRITZ Hydro and VUJE consortium, exceeded €465 million against an estimated value of €371 million, SITA wrote in August.

Context. Gabčíkovo has an installed capacity of 720 MW and is Slovakia's largest hydropower plant. It generates about 2.2 TWh a year on average, equivalent to roughly 8% of the country's annual electricity consumption. Its eight existing turbine-generators were commissioned between 1992 and 1995. On its project page, VVB says the first €30 million grant, awarded in 2025, also concerns two units and includes integrating artificial-intelligence modules into the control systems.

What next. In August the contract with the consortium had not yet been signed, and its duration was planned at about nine years, according to SITA.

Real-time data for the country are on the country page

More news

Comments

Be the first to comment.

Comments appear after the newsroom approves them.

← All the news

Solar calculatorWhat it costs, and how long until it pays for itself.Panels, panels with a battery, or just a battery if you already have panels. The calculator uses the solar radiation where you live, your household's consumption and local energy prices to estimate the cost, the yearly saving and the payback period.Open the page